Perth, April 28, 2025 (GLOBE NEWSWIRE) — PERSEUS MINING PROCEEDS WITH DEVELOPMENT OF THE NYANZAGA GOLD PROJECT

Financial Post

THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

Subscribe now to read the latest news in your city and across Canada.

  • Exclusive articles from Barbara Shecter, Joe O'Connor, Gabriel Friedman, and others.
  • Daily content from Financial Times, the world's leading global business publication.
  • Unlimited online access to read articles from Financial Post, National Post and 15 news sites across Canada with one account.
  • National Post ePaper, an electronic replica of the print edition to view on any device, share and comment on.
  • Daily puzzles, including the New York Times Crossword.

SUBSCRIBE TO UNLOCK MORE ARTICLES

Subscribe now to read the latest news in your city and across Canada.

  • Exclusive articles from Barbara Shecter, Joe O'Connor, Gabriel Friedman and others.
  • Daily content from Financial Times, the world's leading global business publication.
  • Unlimited online access to read articles from Financial Post, National Post and 15 news sites across Canada with one account.
  • National Post ePaper, an electronic replica of the print edition to view on any device, share and comment on.
  • Daily puzzles, including the New York Times Crossword.

REGISTER / SIGN IN TO UNLOCK MORE ARTICLES

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account.
  • Share your thoughts and join the conversation in the comments.
  • Enjoy additional articles per month.
  • Get email updates from your favourite authors.

THIS ARTICLE IS FREE TO READ REGISTER TO UNLOCK.

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account
  • Share your thoughts and join the conversation in the comments
  • Enjoy additional articles per month
  • Get email updates from your favourite authors

Sign In or Create an Account

or

Article content

Article content

overview

Article content

Perth, Western Australia/ April 28, 2025/ Perseus Mining Limited (ASX/TSX: PRU) is pleased to announce that a Final Investment Decision (FID) has been taken to develop the Nyanzaga Gold Project (NGP) in Tanzania, following an update of the NGP Feasibility Study (FS).

Article content

Perseus has committed to invest approximately US$523 million (including contingency) to develop and prepare for the operation of the mine that is expected to produce first gold in Q1 2027. The NGP development will be solely financed via interest free, intercompany loans provided by Perseus from its existing cash and bullion balance of US$801 million as of 31 March 2025.

Article content

Article content

In anticipation of an affirmative FID, Perseus has spent approximately US$27.5 million to date to build project team capacity and commence early works that include site establishment, installation of temporary construction accommodation, and bulk earthworks as well as implementing the Relocation Action Plan (RAP) to construct new dwellings for people impacted by future construction and operating activities.

Article content

By signing up you consent to receive the above newsletter from Postmedia Network Inc.

Article content

The updated FS incorporates findings and recommendations from a range of comprehensive technical assessments made by Perseus’s technical team. Notably, Perseus has opted for a large scale, wholly open-pit mining operation, for the first phase of development, in preference to a smaller scale, combined open pit – underground option contemplated by the previous owners. Key metrics associated with the NGP include the following:

Article content

Article content

Production & Cost Metrics (100% basis):

Article content

  • Total gold production over an 11-year, Phase 1 mine life is currently estimated to be 2.01 Moz based on a JORC 2012 Probable Ore Reserve of 52.0 Mt @ 1.40 g/t gold for 2.3 Moz.
  • Gold production averages over 200,000 ounces of gold per annum from FY28 to FY35, with peak production of 246,000 ounces in FY28.
  • Over the life of the mine, the estimated average All-In Site Cost (AISC) is US$1,211/oz.
  • Capital cost for the plant and site infrastructure is estimated at US$472 million inclusive of US$49 million of contingency, and pre-production capital of US$51 million, giving a total capital cost to first gold pour of US$523 million.

Article content

Investment Metrics (100% basis)1

Article content

Applying Perseus’s assumed long-term gold price of
US$2,100/oz, the NGP’s investment metrics include:

Article content

  • Undiscounted free cashflow pre-tax of US$1,133 million and post-tax of US$706 million, (or US$2,252 million pre-tax and US$1,471 million post-tax at a gold price of US$2,700/oz.)
  • Net Present Value (NPV10%) of US$404 million pre-tax and US$202 million post-tax, (or US$1,010 million pre-tax and US$617 million post-tax at a gold price of US$2,700/oz).
  • Internal Rate of Return (IRR) of 26% pre-tax and 19% post-tax (or 45% pre-tax and 34% post-tax at a gold price of US$2,700/oz).