Eldorado Gold Reports Solid Q3 2025 Financial and Operational Results; Skouries On Track for Q1 2026

6 hours ago 2

Article content

Olympias

Article content

Olympias produced 13,597 ounces of gold in Q3 2025, a decrease from 21,211 ounces in Q3 2024 , driven by lower tonnes milled and lower gold grades. As a result of flotation circuit stability issues earlier in the year, the paste backfill blend was modified to eliminate viscosity modifiers in the backfilled stopes. While plant operations recovered substantially in early Q2, affected stockpiled ore continued to be processed in Q3, and ongoing efforts to minimize negative impacts in the processing circuit were challenged by continued process water chemistry issues, which negatively impacted metal recovery in the quarter. Mitigation measures remain in place; however modest negative impacts on metal recovery may continue to persist as material is processed from affected backfill stopes and affected stockpiles.

Article content

Revenue increased to $65.8 million in Q3 2025 from $65.7 million in Q3 2024, due to higher average realized gold price, offset by lower ounces sold.

Article content

Production costs increased to $45.8 million in Q3 2025 from $44.7 million in Q3 2024. While fewer ounces were produced, costs were higher this quarter than Q3 2024 primarily due to the strengthened Euro as well as higher royalties as a result of higher gold prices. These impacts were partially offset by realized gains on Euro foreign currency collar hedges. In addition to higher production costs, lower by-product credits from lower base metal sales resulted in total cash costs per ounce sold increasing to $1,869 in Q3 2025 from $1,210 in Q3 2024.

Article content

Article content

AISC per ounce sold increased to $2,421 in Q3 2025 from $1,513 in Q3 2024 primarily due to higher total cash costs, lower volumes sold and higher sustaining capital expenditures.

Article content

Sustaining capital expenditures of $6.9 million in Q3 2025 and $17.6 million in the nine months ended September 30, 2025 primarily included underground development, and mobile mining equipment rebuilds and purchases. Growth capital investment of $9.0 million in Q3 2025 and $17.9 million in the nine months ended September 30, 2025 was primarily related to underground development and other mill expansion infrastructure.

Article content

Recognizing persistent operational challenges, initiatives have been launched in Q3 to drive sustainable improvement and long-term success. These include a comprehensive site rejuvenation program focused on modernizing and optimizing the process plant and surrounding infrastructure and a targeted leadership and skills development program aimed at strengthening capabilities across all levels of the organization.

Article content

The mill expansion to 650ktpa (from 500ktpa currently) continued to progress with progressive commissioning and ramp up expected in the second half of 2026.
For further information on the Company’s operating results for the third quarter of 2025, please see the Company’s MD&A filed on SEDAR+ at www.sedarplus.com under the Company’s profile.

Article content

Conference Call

Article content

A conference call to discuss the details of the Company’s Third Quarter 2025 Results will be held by senior management on Friday, October 31, 2025 at 11:30 AM ET (8:30 AM PT). The call will be webcast and can be accessed at Eldorado’s website: www.eldoradogold.com or via this link:
https://event.choruscall.com/mediaframe/webcast.html?webcastid=qOUEmw8O

Article content

Participants may elect to pre-register for the conference call via this link: https://dpregister.com/sreg/10202675/ffd74227dc

Article content

Upon registration, participants will receive a calendar invitation by email with dial in details and a unique PIN. This will allow participants to bypass the operator queue and connect directly to the conference. Registration will remain open until the end of the conference call.

Article content

Conference Call Details Replay (available until Dec. 12, 2025)
Date:October 31, 2025 Vancouver:+1 412 317 0088
Time:11:30 AM ET (8:30 AM PT) Toll Free:+1 855 669 9658
Dial in:+1 647 846 2782 Access code:7168908
Toll free:+1 833 752 3325   

Article content


About Eldorado

Article content

Eldorado is a gold and base metals producer with mining, development and exploration operations in Turkiye, Canada and Greece. The Company has a highly skilled and dedicated workforce, safe and responsible operations, a portfolio of high-quality assets, and long-term partnerships with local communities. Eldorado’s common shares trade on the Toronto Stock Exchange (TSX: ELD) and the New York Stock Exchange (NYSE: EGO).

Article content

Contact

Article content

Investor Relations

Article content

Lynette Gould, VP, Investor Relations, Communications & External Affairs
647 271 2827 or 1 888 353 8166
[email protected]

Article content

Media

Article content

Chad Pederson, Director, Communications and Public Affairs
236 885 6251 or 1 888 353 8166
[email protected]

Article content

Non-IFRS and Other Financial Measures and Ratios

Article content

Certain non-IFRS financial measures and ratios are included in this news release, including total cash costs and total cash costs per ounce sold, all-in sustaining costs (“AISC”) and AISC per ounce sold, sustaining and growth capital, average realized gold price per ounce sold, earnings before interest, taxes, depreciation and amortization (“EBITDA”), adjusted earnings before interest, taxes, depreciation and amortization (“Adjusted EBITDA”), adjusted net earnings/(loss) attributable to shareholders, adjusted net earnings/(loss) per share attributable to shareholders, free cash flow, free cash flow excluding Skouries, and cash flow from operating activities before changes in working capital.

Article content

Please see the September 30, 2025 MD&A for explanations and discussion of these non-IFRS and other financial measures and ratios. The Company believes that these measures and ratios, in addition to conventional measures and ratios prepared in accordance with International Financial Reporting Standards (“IFRS”), provide investors an improved ability to evaluate the underlying performance of the Company. The non-IFRS and other financial measures and ratios are intended to provide additional information and should not be considered in isolation or as a substitute for measures or ratios of performance prepared in accordance with IFRS. These measures and ratios do not have any standardized meaning prescribed under IFRS, and therefore may not be comparable to other issuers. Certain additional disclosures for these and other financial measures and ratios have been incorporated by reference and can be found in the section ‘Non-IFRS and Other Financial Measures and Ratios’ in the September 30, 2025 MD&A available on SEDAR+ at www.sedarplus.com and on the Company’s website under the ‘Investors’ section.

Article content

Total Cash Costs, Total Cash Costs per Ounce Sold

Article content

Our reconciliation of total cash costs and total cash costs per ounce sold to production costs, the most directly comparable IFRS measure, is presented below.

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Production costs$164.1 $141.2 $474.6 $392.0 
By-product credits and other(1) (27.0) (26.9) (68.4) (64.3)
Concentrate deductions(2)$2.1 $3.7 $7.0 $11.2 
Total cash costs$139.3 $118.0 $413.2 $339.0 
Gold ounces sold 116,529  123,828  364,281  361,062 
Total cash cost per ounce sold$1,195 $953 $1,134 $939 

Article content

(1)Revenue from silver, lead and zinc sales.
(2)Included in revenue.

Article content


For the three months ended September 30, 2025:

Article content

 Direct operating costs By-product credits and other Refining and selling costs Inventory change(1) Royalty expense Total cash costs Gold oz sold Total cash cost/oz sold
Kisladag$43.5  ($1.3) $0.2  ($5.8) $12.3 $48.8 37,300 $1,309
Lamaque 34.3  (0.7)  0.1  (0.3)  1.8  35.3 46,013  767
Efemcukuru 19.5  (2.4)  2.9  2.1   8.2  30.5 20,031  1,522
Olympias 38.5  (22.7)  4.0  (1.5)  6.4  24.6 13,185  1,869
Total consolidated$135.8  ($27.0) $7.2  ($5.5) $28.8 $139.3 116,529 $1,195

Article content

(1)Inventory change adjustments result from timing differences between when costs are incurred to produce inventory and when inventory is sold.

Article content


For the nine months ended September 30, 2025:

Article content

 Direct operating costs By-product credits and other Refining and selling costs Inventory change(1) Royalty expense Total cash costs Gold oz sold Total cash cost/oz sold
Kisladag$126.4  ($4.2) $0.6  ($12.8) $36.2 $146.2 126,928 $1,152
Lamaque 101.2  (1.6)  0.3  1.2   5.1  106.2 137,665  772
Efemcukuru 56.9  (5.7)  10.2  0.4   20.4  82.4 58,600  1,405
Olympias 111.5  (56.9)  11.1  (5.0)  17.9  78.5 41,088  1,910
Total consolidated$395.9  ($68.4) $22.3  ($16.2) $79.6 $413.2 364,281 $1,134

Article content

(1)Inventory change adjustments result from timing differences between when costs are incurred to produce inventory and when inventory is sold.

Article content


For the three months ended September 30, 2024:

Article content

 Direct operating costs By-product credits and other Refining and selling costs Inventory change(1) Royalty expense Total cash costs Gold oz sold Total cash cost/oz sold
Kisladag$36.1  ($0.7) $0.1  ($6.8) $7.9 $36.6 40,724 $899
Lamaque 32.4  (0.4)  0.1  (1.0)  1.3  32.4 44,531  728
Efemcukuru 18.0  (1.4)  3.7  (0.2)  6.0  26.2 19,741  1,325
Olympias 38.6  (24.4)  4.6  (1.8)  5.8  22.8 18,833  1,210
Total consolidated$125.2  ($26.9) $8.5  ($9.8) $21.0 $118.0 123,828 $953

Article content

(1)Inventory change adjustments result from timing differences between when costs are incurred to produce inventory and when inventory is sold.

Article content


For the nine months ended September 30, 2024:

Article content

 Direct operating costs By-product credits and other Refining and selling costs Inventory change(1) Royalty expense Total cash costs Gold oz sold Total cash cost/oz sold
Kisladag$105.3  ($2.5) $0.6  ($19.4) $20.1 $104.0 117,068 $889
Lamaque 100.8  (1.3)  0.3  (3.3)  3.7  100.3 132,776  755
Efemcukuru 51.1  (4.7)  11.4  (0.6)  15.0  72.1 60,817  1,185
Olympias 96.5  (55.8)  13.9  (6.2)  14.2  62.6 50,401  1,241
Total consolidated$353.7  ($64.3) $26.1  ($29.5) $53.0 $339.0 361,062 $939

Article content

(1)Inventory change adjustments result from timing differences between when costs are incurred to produce inventory and when inventory is sold.

Article content


All-in Sustaining Costs, All-in Sustaining Costs per Ounce Sold

Article content

Our reconciliation of AISC and AISC per ounce sold to total cash costs is presented below. The reconciliation of total cash costs to production costs, the most directly comparable IFRS measure, is presented above.

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Total cash costs$139.3$118.0$413.2$339.0
Corporate and allocated G&A 15.2 10.9 40.1 35.3
Exploration and evaluation costs 0.6 0.8 1.0 2.8
Reclamation costs and amortization 2.4 2.3 7.3 2.8
Sustaining capital expenditure 38.3 33.3 115.2 93.2
AISC$195.7$165.3$576.8$473.1
Gold ounces sold 116,529 123,828 364,281 361,062
AISC per ounce sold$1,679$1,335$1,583$1,310

Article content

Reconciliations of adjustments within AISC to the most directly comparable IFRS measures are presented below.

Article content

Reconciliation of general and administrative expenses included in All-in Sustaining Costs:

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
General and administrative expenses(from consolidated statement of operations)$8.8 $7.3 $25.4 $27.0 
Add:    
Share-based payments expense 6.8  4.1  15.3  9.8 
Employee benefit plan expense from corporate and operating gold mines 0.7  1.1  2.8  3.2 
Less:    
General and administrative expenses related to non-gold mines and in-country offices   (0.2)   (1.0)
Depreciation in G&A (0.5) (0.9) (1.4) (2.6)
Business development (0.2) (0.3) (0.8) (0.8)
Development projects (0.4) (0.2) (1.3) (0.7)
Adjusted corporate general and administrative expenses$15.2 $10.8 $40.1 $34.9 
Regional general and administrative costs allocated to gold mines (0.1) 0.1  (1.4) 0.5 
Corporate and allocated general and administrative expenses per AISC$15.1 $10.9 $38.6 $35.3 

Article content


Reconciliation of exploration and evaluation costs included in All-in Sustaining Costs:

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Exploration and evaluation expense(from consolidated statement of operations)(1)$11.0 $8.3 $25.2 $16.1 
Add:    
Capitalized sustaining exploration cost related to operating gold mines 0.6  0.8  1.0  2.8 
Less:    
Exploration and evaluation expenses related to non-gold mines and other sites (11.0) (8.3) (25.2) (16.1)
Exploration and evaluation costs per AISC$0.6 $0.8 $1.0 $2.8 

Article content

(1)Amounts presented are from continuing operations only and exclude the Romania segment.

Article content


Reconciliation of reclamation costs and amortization included in All-in Sustaining Costs:

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Asset retirement obligation accretion(from notes to the condensed consolidated interim financial statements)(1)$1.5 $1.2 $4.4 $3.7 
Add:    
Depreciation related to asset retirement obligation assets 1.1  1.3  3.5  (0.2)
Less:    
Asset retirement obligation accretion related to non-gold mines and other sites (0.2) (0.2) (0.7) (0.6)
Reclamation costs and amortization per AISC$2.4 $2.3 $7.3 $2.8 

Article content

(1)Amounts presented are from continuing operations only and exclude the Romania segment.

Article content


Sustaining and Growth Capital

Article content

Our reconciliation of growth capital investment and sustaining capital expenditure at operating gold mines to additions to property, plant and equipment, the most directly comparable IFRS measure, is presented below.

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Additions to property, plant and equipment
(from segment note in the condensed consolidated interim financial statements)(1)
$255.6 $158.1 $669.8 $445.8 
Growth and development project capital investment – gold mines (58.0) (39.0) (143.7) (114.1)
Growth and development project capital investment – other (159.5) (84.7) (408.0) (234.8)
Sustaining capital exploration (0.6) (0.8) (1.0) (2.8)
Sustaining equipment leases 1.2  (0.1) (0.7) 0.6 
Corporate leases (0.4) (0.1) (1.1) (1.5)
Sustaining capital expenditure at operating gold mines$38.3 $33.3 $115.2 $93.2 

Article content

(1)Amounts presented are from continuing operations only and exclude the Romania segment.

Article content

Our reconciliation by asset of AISC and AISC per ounce sold to total cash costs is presented below.

Article content

For the three months ended September 30, 2025:

Article content

 Total Cash CostsCorporate & allocated G&AExploration CostsReclamation costs and amortizationSustaining CapexTotal
AISC
Gold Ounces SoldTotal
AISC
Per Ounce sold
Kisladag$48.8 ($0.3) $—$1.8$7.3$57.637,300$1,545
Lamaque 35.3   0.6 0.1 19.2 55.246,013 1,199
Efemcukuru 30.5 0.3   0.2 4.9 35.920,031 1,791
Olympias 24.6    0.4 6.9 31.913,185 2,421
Corporate(1)  15.1     15.1 129
Total consolidated$139.3$15.2 $0.6$2.4$38.3$195.7116,529$1,679

Article content

(1)Excludes general and administrative expenses related to business development activities and projects. Includes share based payments expense and defined benefit pension plan expense. AISC per ounce sold has been calculated using total consolidated gold ounces sold.

Article content


For the nine months ended September 30, 2025:

Article content

 Total Cash CostsCorporate & allocated G&AExploration CostsReclamation costs and amortizationSustaining CapexTotal
AISC
Gold Ounces SoldTotal
AISC
Per Ounce sold
Kisladag$146.2$0.4 $—$5.4$16.0$168.0126,928$1,324
Lamaque 106.2  1.0 0.2 67.3 174.8137,665 1,270
Efemcukuru 82.4 1.0  0.5 14.3 98.158,600 1,674
Olympias 78.5   1.1 17.6 97.241,088 2,367
Corporate(1)  38.6    38.6 106
Total consolidated$413.2$40.1$1.0$7.3$115.2$576.8364,281$1,583

Article content

(1)Excludes general and administrative expenses related to business development activities and projects. Includes share based payments expense and defined benefit pension plan expense. AISC per ounce sold has been calculated using total consolidated gold ounces sold.

Article content


For the three months ended September 30, 2024:

Article content

 Total Cash CostsCorporate & allocated G&AExploration costsReclamation costs and amortizationSustaining capitalTotal
AISC
Gold oz soldTotal
AISC
/ oz sold
Kisladag$36.6 $— $—$1.6$3.7$41.940,724$1,028
Lamaque 32.4  0.4 0.1 20.0 53.044,531 1,189
Efemcukuru 26.2 0.1  0.2 4.7 31.219,741 1,578
Olympias 22.8  0.4 0.4 4.9 28.518,833 1,513
Corporate(1)  10.8    10.8 88
Total consolidated$118.0$10.9$0.8$2.3$33.3$165.3123,828$1,335

Article content

(1)Excludes general and administrative expenses related to business development activities and projects. Includes share based payments expense and defined benefit pension plan expense. AISC per ounce sold has been calculated using total consolidated gold ounces sold.

Article content


For the nine months ended September 30, 2024:

Article content

 Total Cash CostsCorporate & allocated G&AExploration costsReclamation costs and amortizationSustaining capitalTotal
AISC
Gold oz soldTotal
AISC
/ oz sold
Kisladag$104.0 $— $—$4.4 $8.9$117.3117,068$1,002
Lamaque 100.3  1.2 0.4  61.1 163.1132,776 1,228
Efemcukuru 72.1 0.5 1.1 (3.2) 10.7 81.360,817 1,336
Olympias 62.6  0.5 1.1  12.5 76.650,401 1,520
Corporate(1)  34.9     34.9 97
Total consolidated$339.0$35.3$2.8$2.8 $93.2$473.1361,062$1,310

Article content

(1)Excludes general and administrative expenses related to business development activities and projects. Includes share based payments expense and defined benefit pension plan expense. AISC per ounce sold has been calculated using total consolidated gold ounces sold.

Article content


Average Realized Gold Price per Ounce Sold

Article content

Our reconciliation of average realized gold price per ounce sold to revenue, the most directly comparable IFRS measure, is presented below.

Article content

For the three months ended September 30, 2025:

Article content

 RevenueConcentrate deductions(1)Less non-gold revenueGold revenue(2)Gold oz soldAverage realized gold price per ounce sold
Kisladag$130.5 $— ($1.3)$129.237,300$3,463
Lamaque 160.7  (0.7) 160.046,013 3,478
Efemcukuru 77.8 0.6 (2.4) 76.020,031 3,794
Olympias 65.8 1.6 (21.5) 45.813,185 3,473
Total consolidated$434.7$2.1 ($25.9)$411.0116,529$3,527

Article content

(1)Treatment charges, refining charges, penalties and other costs deducted from proceeds from gold concentrate sales.
(2)Includes the impact of provisional pricing adjustments on concentrate sales.

Article content


For the nine months ended September 30, 2025:

Article content

 RevenueConcentrate deductions(1)Less non-gold revenueGold revenue(2)Gold oz soldAverage realized gold price per ounce sold
Kisladag$410.1 $— ($4.2)$405.9126,928$3,198
Lamaque 447.5  (1.6) 445.9137,665 3,239
Efemcukuru 205.9 2.5 (5.7) 202.858,600 3,460
Olympias 178.2 4.5 (55.2) 127.441,088 3,102
Total consolidated$1,241.7$7.0 ($66.7)$1,182.0364,281$3,245

Article content

(1)Treatment charges, refining charges, penalties and other costs deducted from proceeds from gold concentrate sales.
(2)Includes the impact of provisional pricing adjustments on concentrate sales.

Article content


For the three months ended September 30, 2024:

Article content

 RevenueConcentrate deductions(1)Less non-gold revenueGold revenue(2)Gold oz soldAverage realized gold price per ounce sold
Kisladag$102.2 $— ($0.7)$101.540,724$2,492
Lamaque 111.6  (0.4) 111.244,531 2,496
Efemcukuru 52.3 1.1 (1.4) 52.019,741 2,636
Olympias 65.7 2.6 (24.4) 43.818,833 2,328
Total consolidated$331.8$3.7 ($26.9)$308.5123,828$2,492

Article content

(1)Treatment charges, refining charges, penalties and other costs deducted from proceeds from gold concentrate sales.
(2)Includes the impact of provisional pricing adjustments on concentrate sales.

Article content


For the nine months ended September 30, 2024:

Article content

 RevenueConcentrate deductions(1)Less non-gold revenueGold revenue(2)Gold oz soldAverage realized gold price per ounce sold
Kisladag$273.3 $— ($2.5)$270.8117,068$2,313
Lamaque 307.8  (1.3) 306.6132,776 2,309
Efemcukuru 148.9 3.8 (4.7) 148.060,817 2,433
Olympias 156.8 7.5 (55.8) 108.550,401 2,152
Total consolidated$886.9$11.2 ($64.3)$833.8361,062$2,309

Article content

(1)Treatment charges, refining charges, penalties and other costs deducted from proceeds from gold concentrate sales.
(2)Includes the impact of provisional pricing adjustments on concentrate sales.

Article content


EBITDA, Adjusted EBITDA

Article content

Our reconciliation of EBITDA and Adjusted EBITDA to earnings (loss) from continuing operations before income tax, the most directly comparable IFRS measure, is presented below.

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Earnings before income tax(1)$110.1 $129.3 $324.6 $258.5 
Depreciation and amortization(2) 63.3  64.9  190.4  180.6 
Interest income (8.6) (6.1) (25.8) (17.3)
Finance costs 8.2  3.5  21.1  10.5 
EBITDA$173.1 $191.6 $510.3 $432.3 
Loss (gain) on disposal of assets 0.4  0.3  (6.6) 0.8 
Unrealized loss on derivative instruments 22.2  33.1  66.8  61.9 
Loss (gain) on recognition of deferred consideration(3) 0.5  (60.0) 0.5  (60.0)
Adjusted EBITDA$196.3 $164.9 $571.1 $435.1 

Article content

(1)Amounts presented are from continuing operations only and exclude the Romania segment.
(2)Includes depreciation within general and administrative expenses.
(3)In Q3 2025, transaction costs of $0.5 million were recognized against the $60 million gain in Q3 2024 related to deferred consideration from the sale of the Tocantinzinho property to G Mining Ventures in 2021.

Article content


Adjusted Net Earnings (Loss), Adjusted Net Earnings (Loss) per Share

Article content

Our reconciliation of adjusted net earnings (loss) and adjusted net earnings (loss) per share to net earnings (loss) from continuing operations attributable to shareholders of the Company, the most directly comparable IFRS measure, is presented below.

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Net earnings attributable to shareholders of the Company(1)$56.5 $101.1 $267.5 $192.7 
Loss (gain) on foreign exchange translation of deferred tax balances net of inflation accounting(2) 3.7  (15.3) (22.6) (11.9)
Increase in fair value of redemption option derivative (0.7) (5.0) (8.6) (7.0)
Unrealized loss on derivative instruments 22.2  33.1  66.8  61.9 
Tax recovery on recognition of deferred tax asset     (73.5)  
Discount on sale of marketable securities     5.1   
Gain on sale of mining licenses     (6.5)  
Tax reassessment on historical items(3)   7.2    7.2 
Loss (gain) on deferred consideration, net of tax(4) 0.5  (50.1) 0.5  (50.1)
Total adjusted net earnings$82.3 $71.0 $228.8 $192.9 
Weighted average shares outstanding (thousands) 202,743  204,521  204,130  203,770 
Adjusted net earnings per share ($/share)$0.41 $0.35 $1.12 $0.95 

Article content

(1)Amounts presented are from continuing operations only and exclude the Romania segment.
(2)Q3 2025 includes $3.7 million loss (2024 – $8.3 million gain) on foreign exchange translation of deferred tax balances and $nil (2024 – $7.0 million gain) on Turkiye tax inflation accounting. Nine months ended September 30, 2025 includes $22.6 million gain (2024 – $16.7 million loss) on foreign exchange translation of deferred tax balances and $nil (2024 – $28.6 million gain) on Turkiye tax inflation accounting.
(3)A provision of $7.2 million was recorded for potential non-recurring tax reassessments represent $5.9 million of tax and $1.4 million of interest. These relate to historical intercompany loan balances in 2020 and 2021 which have since been capitalized.
(4)In Q3 2025, transaction costs of $0.5 million were recognized upon collection of deferred consideration (Q3 2024: a $60 million gain related to the deferred consideration from the sale of the Tocantinzinho property to G Mining Ventures in 2021 was recognized, net of taxes of $9.9 million).

Article content


Free Cash Flow and Free Cash Flow Excluding Skouries

Article content

Our reconciliations of free cash flow and free cash flow excluding Skouries to net cash generated from (used in) operating activities from continuing operations, the most directly comparable IFRS measure, is presented below.

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Net cash generated from operating activities(1)$170.2 $180.9 $458.8 $388.4 
Less: Cash used in investing activities (212.1) (184.2) (434.1) (464.7)
Less: Decrease in term deposits       (1.1)
Less: Proceeds from sale of mining licenses   (1.5) (2.5) (1.5)
Add back (less): Purchases (proceeds from sale) of marketable securities 14.0    (141.1) 11.1 
Less: Cash received from deferred consideration(2) (59.5)   (59.5)  
Free cash flow ($87.4) ($4.8) ($178.4) ($67.8)
Add back: Skouries cash capital expenditures 155.9  93.9  356.2  210.4 
Add back: Capitalized interest paid(3) 8.4  9.1  28.5  23.2 
Free cash flow excluding Skouries$76.9 $98.3 $206.3 $165.8 

Article content

(1)Amounts presented are from continuing operations only and exclude the Romania segment.
(2)Deferred consideration received from G Mining Ventures of $60 million, net of transaction costs of $0.5 million.
(3)Includes interest from the Term Facility and Senior Notes.

Article content


Cash Flow from Operating Activities before Changes in Working Capital

Article content

Our reconciliation of cash flow from operating activities before changes in working capital to net cash generated from (used in) operating activities from continuing operations, the most directly comparable IFRS measure, is presented below.

Article content

 Q3 2025Q3 2024YTD 2025YTD 2024
Net cash generated from operating activities(1)$170.2$180.9 $458.8$388.4
Add back (less): Changes in non-cash working capital 13.3 (14.4) 63.2 18.6
Cash flow from operating activities before changes in working capital$183.5$166.5 $522.0$407.0

Article content

(1)Amounts presented are from continuing operations only and exclude the Romania segment.

Article content


Forward-looking Statements and Information

Article content

Certain of the statements made and information provided in this news release are forward-looking statements or forward-looking information within the meaning of the United States Private Securities Litigation Reform Act of 1995 and applicable Canadian securities laws. Often, these forward-looking statements and forward-looking information can be identified by the use of words such as “anticipates”, “believes”, “budgets”, “committed”, “continue”, “estimates”, “expects”, “focus”, “forecasts”, “foresee”, “forward”, “future”, “goal”, “guidance”, “intends”, “opportunity”, “outlook”, “plans”, “potential”, “schedule”, “strategy”, “target”, “underway”, “working” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “can”, “could”, “likely”, “may”, “might”, “will” or “would” be taken, occur or be achieved.
Forward-looking statements and forward-looking information contained in this news release includes, but is not limited to, statements or information with respect to: 2025 production and cost outlook, including annual production guidance and expected production performance in the second half of the year (for various properties), expected total cash costs per ounce sold, all-in sustaining costs per ounce sold, operations growth capital, sustaining capital, and exploration expenditures; management’s views on achieving guidance; management’s commitment to returning capital to shareholders; with respect to the Skouries Project; the timing of first production, expected mine life and average annual gold and copper production; timing of commercial production and expected 2026 gold and copper production; expected 2025 project capital spend and accelerated operational capital spend; specific activities and milestones anticipated to occur with respect to construction, development, engineering, procurement and operational readiness; with respect to Kisladag, the decision to proceed with and expected benefits of the whole ore agglomeration project and the timing thereof, expectations for extending mine life and construction of the second phase of the North Heap Leach Pad, timing of the expansion of the secondary crusher circuit, expected timing of results from the geometallurgical study; with respect to the Lamaque Complex, expected development at Ormaque; with respect to Efemcukuru, underground development at Kokarpinar and development at Bati; with respect to Olympias, expectations for the mill expansion and anticipated timing thereof, management’s views with respect to impacts on future metal recovery and the underlying causes related thereto; and expected benefits of a site rejuvenation and leadership and skills development; non-IFRS financial measures and ratios; expected metallurgical recoveries and gold price outlook; and generally our strategy, plans and goals, including our proposed exploration, development, construction, permitting, financing and operating potential, plans and priorities and related timelines and schedules.

Article content

Forward-looking statements and forward-looking information are by their nature based on a number of assumptions, that management considers reasonable. However, such assumptions involve both known and unknown risks, uncertainties, and other factors which, if proven to be inaccurate, may cause actual results, activities, performance or achievements may be materially different from those described in the forward-looking statements or information. These include assumptions concerning: timing, cost and results of our construction and development activities, improvements and exploration; the future price of gold and other commodities; exchange rates; anticipated values, costs, expenses and working capital requirements; production and metallurgical recoveries; mineral reserves and resources; our ability to unlock the potential of our brownfield property portfolio; our ability to address the negative impacts of climate change and adverse weather; consistency of agglomeration and our ability to optimize it in the future; the cost of, and extent to which we use, essential consumables (including fuel, explosives, cement, and cyanide); the impact and effectiveness of productivity initiatives; the time and cost necessary for anticipated overhauls of equipment; expected by-product grades; the use, and impact or effectiveness, of growth capital; the impact of acquisitions, dispositions, suspensions or delays on our business; the sustaining capital required for various projects; and the geopolitical, economic, permitting and legal climate that we operate in.

Article content

More specifically, with respect to the Skouries Project and updates, we have made additional assumptions regarding: our ability and our contractors’ ability to recruit and retain labour resources within the required timeline; labour productivity, rates, and expected hours; inflation rates; the expected scope of project management frameworks; our ability to continue executing our plans relating to the Skouries Project on the estimated existing project timeline and consistent with the current planned project scope (including our anticipated progress regarding the Integrated Extractive Waste Management Facility (“IEWMF”) and two underground test stopes); the timeliness of shipping for important or critical items; our ability to continue accessing our project funding and remain in compliance with all covenants and contractual commitments related thereto; our ability to obtain and maintain all required approvals and permits, both overall and in a timely manner; the absence of further previously unidentified archaeological discoveries which would delay construction of various portions of the project; the future price of gold, copper, and other commodities; and the broader community engagement and social climate in respect of the Skouries Project.

Article content

In addition, except where otherwise stated, Eldorado has assumed a continuation of existing business operations on substantially the same basis as exists at the time of this news release. Even though we believe that the assumptions and expectations represented by such statements or information are reasonable, there can be no assurance that the forward-looking statement or information will prove to be accurate. Many assumptions may be difficult to predict and are beyond our control.

Article content

Forward-looking statements and forward-looking information are subject to known and unknown risks, uncertainties and other important factors that may cause actual results, activities, performance or achievements to be materially different from those described in the forward-looking statements or information. These risks, uncertainties and other factors include, among others: development risks at Skouries and other development projects; risks relating to our operations in foreign jurisdictions; risks related to production and processing; our ability to secure supplies of power and water at a reasonable cost; prices of commodities and consumables; our reliance on significant amounts of critical equipment; our reliance on infrastructure, commodities and consumables; inflation risk; community relations and social license; environmental matters; geotechnical and hydrogeological conditions or failures; waste disposal; mineral tenure; permits; non-governmental organizations; reputational issues; climate change; change of control; actions of activist shareholders; estimation of Mineral Reserves and Mineral Resources; regulatory reviews and different standards used to prepare and report Mineral Reserves and Mineral Resources; risks relating to any pandemic, epidemic, endemic, or similar public health threats; regulated substances; acquisitions, including integration risks; dispositions; co-ownership of our properties; investment portfolio; volatility, volume fluctuations, and dilution risk in respect of our shares; competition; reliance on a limited number of smelters and off-takers; information and operational technology systems; liquidity and financing risks; indebtedness (including current and future operating restrictions, implications of a change of control, ability to meet debt service obligations, the implications of defaulting on obligations and changes in credit ratings); total cash costs per ounce and AISC (particularly in relation to the market price of gold and the Company’s profitability); currency risk; interest rate risk; credit risk; tax matters; financial reporting (including relating to the carrying value of our assets and changes in reporting standards); the global economic environment; labour (including in relation to employee/union relations, the Greek transformation, employee misconduct, key personnel, skilled workforce, expatriates, and contractors); commodity price risk; default on obligations; current and future operating restrictions; reclamation and long-term obligations; credit ratings; change in reporting standards; the unavailability of insurance; Sarbanes-Oxley Act, applicable securities laws, and stock exchange rules; risks relating to environmental, sustainability, and governance practices and performance; corruption, bribery, and sanctions; employee misconduct; litigation and contracts; conflicts of interest; compliance with privacy legislation; dividends; tariffs and other trade barriers; and those risk factors discussed in our most recent Annual Information Form & Form 40-F. The reader is directed to carefully review the detailed risk discussion in our most recent Annual Information Form & Form 40-F filed on SEDAR+ and EDGAR under our Company name, which discussion is incorporated by reference in this news release, for a fuller understanding of the risks and uncertainties that affect our business and operations.

Article content

With respect to the Skouries Project, these risks, uncertainties and other factors may cause further delays in the completion of the construction and commissioning at the Skouries Project which in turn may cause delays in the commencement of production, and further increase to the costs of the Skouries Project. The specific risks, certainties and other factors include, among others: increase the costs of the Skouries Project. The specific risks, uncertainties and other factors include, among others: our ability, and the ability of our construction contractors to recruit the required number of personnel (both skilled and unskilled) with required skills within the required timelines, and to manage changes to workforce numbers through the construction of the Skouries Project; our ability to recruit personnel having the requisite skills, experience, and ability to work on site; our ability to increase productivity by adding or modifying labour shifts; rising labour costs or costs of key inputs such as materials, power and fuel; risks related to third-party contractors, including reduced control over aspects of the Company’s operations, and/or the ability of contractors to perform at required levels and according to baseline schedules ; the ability of key suppliers to meet key contractual commitments in terms of schedules, amount of product delivered, cost, or quality; our ability to construct key infrastructure within the required timelines, including the process plant, filter plant, waste management facilities, and embankments; differences between projected and actual degree of pre-strip required in the open pit; variability in metallurgical recoveries and concentrate quality due to factors such as extent and intensity of oxidation or presence of transition minerals; presence of additional structural features impacting hydrological and geotechnical considerations; variability in minerals or presence of substances that may have an impact on filtered tails performance and resulting bulk density of stockpiles or filtered tails; distribution of sulfides that may dilute concentrate and change the characteristics of tailings; unexpected disruptions to operations due to protests, non-routine regulatory inspections, road conditions, or labour unrest; unexpected inclement weather and climate events, including short and long duration rainfall and floods; our ability to meet pre-commercial producing mining or underground development targets; unexpected results from underground stopes; new archaeological discoveries requiring the completion of a regulatory process; changes in support from local communities; our ability to meet the expectations of communities, governments, and stakeholders related to the Skouries Project; and timely receipt of necessary permits and authorizations. Our project capital and accelerated operational capital costs at Skouries are incurred primarily in Euros but are reported in US dollars and are therefore sensitive to fluctuations in the EUR:USD exchange rate.

Article content

The inclusion of forward-looking statements and information is designed to help you understand management’s current views of our near- and longer-term prospects, and it may not be appropriate for other purposes. There can be no assurance that forward-looking statements or information will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, you should not place undue reliance on the forward-looking statements or information contained herein. Except as required by law, we do not expect to update forward-looking statements and information continually as conditions change and you are referred to the full discussion of the Company’s business contained in the Company’s reports filed with the securities regulatory authorities in Canada and the United States.

Article content

This news release contains information that may constitute future-orientated financial information or financial outlook information (collectively, “FOFI”) about Eldorado’s prospective financial performance, financial position or cash flows, all of which is subject to the same assumptions, risk factors, limitations and qualifications as set forth above. Readers are cautioned that the assumptions used in the preparation of such information, although considered reasonable at the time of preparation, may prove to be imprecise or inaccurate and, as such, undue reliance should not be placed on FOFI. Eldorado’s actual results, performance and achievements could differ materially from those expressed in, or implied by, FOFI. Eldorado has included FOFI in order to provide readers with a more complete perspective on Eldorado’s future operations and management’s current expectations relating to Eldorado’s future performance. Readers are cautioned that such information may not be appropriate for other purposes. FOFI contained herein was made as of the date of this news release. Unless required by applicable laws, Eldorado does not undertake any obligation to publicly update or revise any FOFI statements, whether as a result of new information, future events or otherwise.

Article content

Mineral Reserves and Mineral Resources Estimates and Related Cautionary Note to U.S. Investors

Article content

The Company’s mineral reserve and mineral resource estimates for Kisladag, Lamaque, Efemcukuru, Olympias, Perama Hill, Perama South, Skouries, Stratoni, Piavitsa, Sapes, Certej, and Ormaque, are based on the definitions adopted by the Canadian Institute of Mining, Metallurgy and Petroleum, and in compliance with NI 43-101. NI 43-101 is a rule developed by the Canadian Securities Administrators that establishes standards for all public disclosure an issuer makes of scientific and technical information concerning mineral projects. These standards differ from the requirements of the SEC that are applicable to domestic U.S. companies. The reader may not be able to compare the mineral reserve and mineral resources information in this news release with similar information made public by domestic U.S. companies. The reader should not assume that:

Article content

  • the mineral reserves defined in this news release qualify as reserves under SEC standards
  • the measured and indicated mineral resources in this news release will ever be converted to reserves; and
  • the inferred mineral resources in this news release are economically mineable, or will ever be upgraded to a higher category.

Article content

Mineral resources which are not mineral reserves do not have demonstrated economic viability.

Article content

The Company most recently completed its Mineral Reserves and Mineral Resources annual review process with an effective date of September 30, 2024, a summary of which was published on December 11, 2024. In addition, the Company filed the following Amended Technical Report on SEDAR+ and EDGAR in Q1 2025: Amended Technical Report titled “Technical Report, Lamaque Complex, Quebec, Canada” with an effective date of December 31, 2024. The updated Technical Report does not contain any material changes to the Mineral Resources and Mineral Reserves previously published on December 11, 2024.

Article content

Qualified Person

Article content

Except as otherwise noted, Simon Hille, FAusIMM, Executive Vice President, Technical Services and Operations, is the Qualified Person under NI 43-101 responsible for preparing and supervising the preparation of the scientific and technical information contained in this news release and verifying the technical data disclosed in this document relating to our operating mines and development projects.

Article content

Jessy Thelland, géo (OGQ No. 758), a member in good standing of the Ordre des Géologues du Québec, is the qualified person as defined in NI 43-101 responsible for, and has verified and approved, the scientific and technical disclosure contained in this news release for the Quebec projects.

Article content

Mineral resources that are not mineral reserves do not have demonstrated economic viability. Inferred mineral resources are considered too speculative geologically to have the economic considerations applied to them that would enable them to be categorized as mineral reserves.

Article content

Eldorado Gold Corporation
Condensed Consolidated Interim Statements of Financial Position                

Article content

As at September 30, 2025 and December 31, 2024
(Unaudited – in thousands of U.S. dollars)

Article content

As atNote September 30, 2025 December 31, 2024
      
ASSETS     
Current assets     
Cash and cash equivalents  $1,043,935  $856,797 
Accounts receivable and other4  209,636   190,676 
Inventories5  289,493   278,995 
Current other assets6     138,932 
Current derivative assets16  2,377   52 
Assets held for sale   13,551   16,686 
    1,558,992   1,482,138 
Restricted cash   2,281   2,177 
Deferred tax assets   19,487   19,487 
Other assets6  173,068   120,418 
Non-current derivative assets16  12,614    
Property, plant and equipment   4,626,398   4,118,782 
Goodwill   92,591   92,591 
   $6,485,431  $5,835,593 
LIABILITIES & EQUITY     
Current liabilities     
Accounts payable and accrued liabilities  $472,273  $366,690 
Current portion of lease liabilities   5,759   4,693 
Current portion of asset retirement obligation   5,327   5,071 
Current derivative liabilities16  64,142   25,587 
Liabilities associated with assets held for sale   10,459   10,133 
    557,960   412,174 
Debt7  1,258,517   915,425 
Lease liabilities   9,622   10,030 
Employee benefit plan obligations   12,618   10,910 
Asset retirement obligations   133,864   127,925 
Non-current derivative liabilities16  78,971   35,743 
Deferred income tax liabilities   344,128   434,939 
    2,395,680   1,947,146 
Equity     
Share capital12  3,379,147   3,433,778 
Shares held in trust for restricted share units12  (12,891)  (12,970)
Contributed surplus   2,551,436   2,612,762 
Accumulated other comprehensive income   6,735   56,183 
Deficit   (1,823,222)  (2,193,163)
Total equity attributable to shareholders of the Company   4,101,205   3,896,590 
Attributable to non-controlling interests   (11,454)  (8,143)
    4,089,751   3,888,447 
   $6,485,431  $5,835,593 

Article content

Approved on behalf of the Board of Directors
 (signed)  Teresa ConwayDirector(signed)  George BurnsDirector  
       
Date of approval:October 30, 2025

Article content

Please see the Condensed Consolidated Interim Financial Statements dated September 30, 2025 for notes to the accounts.

Article content


Eldorado Gold Corporation

Condensed Consolidated Interim Statements of Operations        

Article content

For the three and nine months ended September 30, 2025 and 2024
(Unaudited – in thousands of U.S. dollars except share and per share amounts)

Article content

   Three months ended Nine months ended
   September 30, September 30,
 Note  2025   2024   2025   2024 
Revenue         
Metal sales8 $434,727  $331,758  $1,241,696  $886,866 
          
Cost of sales         
Production costs   164,140   141,225   474,609   392,040 
Depreciation and amortization   62,829   64,056   188,961   177,973 
    226,969   205,281   663,570   570,013 
          
Earnings from mine operations   207,758   126,477   578,126   316,853 
          
Exploration and evaluation expenses   10,975   8,310   25,218   16,129 
Mine standby costs   6,465   3,198   15,252   7,821 
General and administrative expenses   8,784   7,281   25,371   27,040 
Employee benefit plan expense   719   1,115   2,820   3,153 
Share-based payments expense13  6,802   4,083   15,347   9,808 
Write-down of assets   3,261   2   8,426   1,412 
Foreign exchange loss   32   2,527   24,840   979 
Earnings from operations   170,720   99,961   460,852   250,511 
          
Other (expense) income9  (52,406)  32,773   (115,145)  18,553 
Finance costs10  (8,221)  (3,476)  (21,134)  (10,529)
Earnings from continuing operations before income tax   110,093   129,258   324,573   258,535 
Income tax expense11  53,917   28,223   54,604   65,986 
Net earnings from continuing operations   56,176   101,035   269,969   192,549 
Net loss from discontinued operations, net of tax   (1,122)  (9,770)  (6,578)  (12,268)
Net earnings for the period  $55,054  $91,265  $263,391  $180,281 
          
Net earnings (loss) attributable to:         
Shareholders of the Company   56,027   94,971   266,438   184,056 
Non-controlling interests   (973)  (3,706)  (3,047)  (3,775)
Net earnings for the period  $55,054  $91,265  $263,391  $180,281 
          
Net earnings (loss) attributable to shareholders of the Company:         
Continuing operations   56,540   101,113   267,522   192,691 
Discontinued operations   (513)  (6,142)  (1,084)  (8,635)
   $56,027  $94,971  $266,438  $184,056 
          
Net (loss) earnings attributable to non-controlling Interests:         
Continuing operations   (364)  (78)  2,447   (142)
Discontinued operations   (609)  (3,628)  (5,494)  (3,633)
   $(973) $(3,706) $(3,047) $(3,775)
          
Weighted average number of shares outstanding:         
Basic12  202,742,582   204,520,670   204,129,778   203,770,089 
Diluted12  205,150,042   206,146,570   206,247,722   205,257,479 
          
Net earnings per share attributable to shareholders of the Company:         
Basic earnings per share  $0.28  $0.46  $1.31  $0.90 
Diluted earnings per share  $0.27  $0.46  $1.29  $0.90 
          
Net earnings per share attributable to shareholders of the Company – Continuing operations:         
Basic earnings per share  $0.28  $0.49  $1.31  $0.95 
Diluted earnings per share  $0.28  $0.49  $1.30  $0.94 

Article content

Please see the Condensed Consolidated Interim Financial Statements dated September 30, 2025 for notes to the accounts.

Article content


Eldorado Gold Corporation

Condensed Consolidated Interim Statements of Comprehensive Income 

Article content

For the three and nine months ended September 30, 2025 and 2024
(Unaudited – in thousands of U.S. dollars)

Article content

   Three months ended Nine months ended
   September 30, September 30,
    2025   2024   2025   2024 
          
Net earnings for the period  $55,054  $91,265  $263,391  $180,281 
Other comprehensive income (loss):         
Items that will not be reclassified to earnings or loss:         
Change in fair value of investments in marketable securities   32,584   2,739   62,521   57,984 
Income tax expense on change in fair value of investments in marketable securities   (4,388)  (339)  (8,394)  (7,787)
Actuarial (losses) gains on employee benefit plans   (359)  413   61   (342)
Income tax (expense) recovery on actuarial losses on employee benefit plans   (32)  (96)  (133)  82 
Total other comprehensive income for the period   27,805   2,717   54,055   49,937 
Total comprehensive income for the period  $82,859  $93,982  $317,446  $230,218 
          
Total comprehensive income (loss) attributable to:         
Shareholders of the Company   83,832   97,688   320,493   233,993 
Non-controlling interests   (973)  (3,706)  (3,047)  (3,775)
   $82,859  $93,982  $317,446  $230,218 

Article content

Please see the Condensed Consolidated Interim Financial Statements dated September 30, 2025 for notes to the accounts.

Article content


Eldorado Gold Corporation

Condensed Consolidated Interim Statements of Cash Flows

Article content

For the three and nine months ended September 30, 2025 and 2024
(Unaudited – in thousands of U.S. dollars)

Article content

   Three months ended Nine months ended
   September 30, September 30,
 Note  2025   2024   2025   2024 
Cash flows generated from (used in):         
Operating activities         
Net earnings from continuing operations  $56,176  $101,035  $269,969  $192,549 
Adjustments for:         
Depreciation and amortization   63,342   64,944   190,374   180,608 
Finance costs10  8,221   3,476   21,134   10,529 
Interest income9  (8,561)  (6,060)  (25,782)  (17,346)
Foreign exchange (gain) loss   (694)  1,797   23,991   3,134 
Income tax expense11  53,917   28,223   54,604   65,986 
Loss (gain) on disposal of assets   441   273   (6,618)  830 
Unrealized loss on derivative contracts9  22,194   33,055   66,844   61,908 
Write-down of assets   3,261   2   8,426   1,412 
Share-based payments expense13  6,802   4,083   15,347   9,808 
Employee benefit plan expense   719   1,115   2,820   3,153 
Non-cash gain on deferred consideration4     (60,000)     (60,000)
    205,818   171,943   621,109   452,571 
Property reclamation payments   (1,284)  (926)  (3,688)  (2,419)
Employee benefit plan payments   (298)  (255)  (1,087)  (1,175)
Income taxes paid   (29,316)  (10,308)  (120,136)  (59,349)
Interest received   8,561   6,060   25,782   17,346 
Changes in non-cash operating working capital14  (13,273)  14,385   (63,194)  (18,575)
Net cash generated from operating activities of continuing operations   170,208   180,899   458,786   388,399 
Net cash (used in) generated from operating activities of discontinued operations   (151)  (75)  158   (293)
          
Investing activities         
Additions to property, plant and equipment   (242,517)  (169,337)  (592,207)  (423,117)
Capitalized interest paid   (8,437)  (9,136)  (28,457)  (23,224)
Proceeds from the sale of property, plant and equipment   244   232   724   248 
Proceeds from sale of mining licenses         2,500    
Value added taxes related to mineral property expenditures, net   (5,954)  (5,968)  (7,005)  (8,593)
Cash received from deferred consideration4  60,000      60,000    
(Purchase) sale of investments in marketable securities   (13,961)     141,117   (11,130)
Deposits on property, plant and equipment   (1,484)     (10,750)   
Decrease in other investments            1,136 
Net cash used in investing activities of continuing operations   (212,109)  (184,209)  (434,078)  (464,680)
          
Financing activities         
Issuance of common shares for cash, net of share issuance costs   1,575   1,340   9,102   13,659 
Contributions from (distributions to) non-controlling interests   53      (264)  173 
Proceeds from Term Facility – Commercial loans and RRF loans7  97,884   92,207   278,494   218,810 
Proceeds from VAT Facility7  26,329   18,034   63,888   37,340 
Repayments of VAT Facility7  (25,664)  (15,473)  (54,068)  (30,962)
Term Facility commitment fees         (1,372)  (2,201)
Interest paid   (9,174)  (10,058)  (19,601)  (20,097)
Principal portion of lease liabilities   (1,401)  (1,202)  (3,927)  (3,366)
Purchase of shares for cancellation12  (78,793)     (123,381)   
Purchase of shares held in trust for restricted share units12  (3,955)     (8,181)  (958)
Net cash generated from financing activities of continuing operations   6,854   84,848   140,690   212,398 
Effect of exchange rates on cash and cash equivalents   410      21,740    
          
Net (decrease) increase in cash and cash equivalents   (34,788)  81,463   187,296   135,824 
          
Cash and cash equivalents – beginning of period   1,078,572   595,052   856,797   540,473 
Change in cash in disposal group held for sale   151   75   (158)  293 
Cash and cash equivalents – end of period  $1,043,935  $676,590  $1,043,935  $676,590 

Article content

Please see the Condensed Consolidated Interim Financial Statements dated September 30, 2025 for notes to the accounts.

Article content

Eldorado Gold Corporation
Condensed Consolidated Interim Statements of Changes in Equity

Article content

For the three and nine months ended September 30, 2025 and 2024
(Unaudited – in thousands of U.S. dollars)

Article content

  Three months ended Nine months ended
  September 30, September 30,
 Note 2025   2024   2025   2024 
Share capital        
Balance beginning of period $3,423,439  $3,431,267  $3,433,778  $3,413,365 
Shares issued upon exercise of share options  1,502   1,465   9,913   13,784 
Shares issued upon redemption of performance share units        5,282   499 
Transfer of contributed surplus on exercise of options  565   595   3,749   5,679 
Shares repurchased and cancelled, including tax  (42,467)     (68,872)   
Shares repurchased and not yet cancelled  (3,892)     (3,892)   
Share issuance costs        (811)   
Balance end of period12$3,379,147  $3,433,327  $3,379,147  $3,433,327 
         
Shares held in trust for restricted share units        
Balance beginning of period $(9,162) $(12,157) $(12,970) $(19,263)
Shares purchased and held in trust for restricted share units  (3,954)     (8,180)  (958)
Shares released for settlement of restricted share units  225   191   8,259   8,255 
Balance end of period12$(12,891) $(11,966) $(12,891) $(11,966)
         
Contributed surplus        
Balance beginning of period $2,583,047  $2,607,572  $2,612,762  $2,617,216 
Shares repurchased and cancelled  (33,876)     (52,950)   
Share-based payment arrangements  3,055   3,064   8,914   7,067 
Shares redeemed upon exercise of restricted share units  (225)  (191)  (8,259)  (8,255)
Shares redeemed upon exercise of performance share units        (5,282)  (499)
Transfer to share capital on exercise of options  (565)  (595)  (3,749)  (5,679)
Balance end of period $2,551,436  $2,609,850  $2,551,436  $2,609,850 
         
Accumulated other comprehensive (loss) income        
Balance beginning of period $(21,070) $42,469  $56,183  $(4,751)
Other comprehensive earnings for the period attributable to shareholders of the Company  27,805   2,717   54,055   49,937 
Reclassification of accumulated other comprehensive income on derecognition of investment in marketable securities $  $  $(103,503) $ 
Balance end of period $6,735  $45,186  $6,735  $45,186 
         
Deficit        
Balance beginning of period $(1,879,249) $(2,399,335) $(2,193,163) $(2,488,420)
Net earnings attributable to shareholders of the Company  56,027   94,971   266,438   184,056 
Reclassification of accumulated other comprehensive income on derecognition of investment in marketable securities $  $  $103,503  $ 
Balance end of period $(1,823,222) $(2,304,364) $(1,823,222) $(2,304,364)
Total equity attributable to shareholders of the Company $4,101,205  $3,772,033  $4,101,205  $3,772,033 
         
Non-controlling interests        
Balance beginning of period $(10,534) $(6,078) $(8,143) $(6,182)
Loss attributable to non-controlling interests  (973)  (3,706)  (3,047)  (3,775)
Contributions from (distributions to) non-controlling interests  53      (264)  173 
Balance end of period $(11,454) $(9,784) $(11,454) $(9,784)
Total equity $4,089,751  $3,762,249  $4,089,751  $3,762,249 

Article content

Please see the Condensed Consolidated Interim Financial Statements dated September 30, 2025 for notes to the accounts.

Article content

____________________
1 These financial measures or ratios are non-IFRS financial measures or ratios. Certain additional disclosure for non-IFRS financial measures and ratios have been incorporated by reference and additional detail can be found at the end of this news release and in the section ‘Non-IFRS and Other Financial Measures and Ratios’ in the Company’s September 30, 2025 MD&A.
2 Term Facility is defined in the Company’s September 30, 2025 condensed consolidated interim financial statements.
3 These financial measures or ratios are non-IFRS financial measures or ratios. Certain additional disclosure for non-IFRS financial measures and ratios have been incorporated by reference and additional detail can be found at the end of this news release and in the section ‘Non-IFRS and Other Financial Measures and Ratios’ in the Company’s September 30, 2025 MD&A.
4 Excludes capitalized depreciation of $1.9 million in Q3 2025, and $5.1 million for the nine-month period ended September 30, 2025 (Q3 2024 – $nil, 2024 – includes $3.2 million) and corporate allocations of $0.3 million in Q3 2025, and $1.0 million for the nine-month period ended September 30, 2025 (Q3 2024 – $nil, 2024 – includes $1.5 million)
5 These financial measures or ratios are non-IFRS financial measures or ratios. Certain additional disclosure for non-IFRS financial measures and ratios have been incorporated by reference and additional detail can be found at the end of this news release and in the section ‘Non-IFRS and Other Financial Measures and Ratios’ in the Company’s September 30, 2025 MD&A.

Article content

Article content

Article content

Article content

Article content

Article content

Read Entire Article