Data Centers in Nvidia’s Hometown Stand Empty Awaiting Power

1 hour ago 3
 Jason Henry/BloombergDigital Realty's SJC37 data center project in Santa Clara. Photographer: Jason Henry/Bloomberg Photo by Jason Henry /Bloomberg

Article content

(Bloomberg) — Two of the world’s biggest data center developers have projects in Nvidia Corp.’s hometown that may sit empty for years because the local utility isn’t ready to supply electricity.

Financial Post

THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

Subscribe now to read the latest news in your city and across Canada.

  • Exclusive articles from Barbara Shecter, Joe O'Connor, Gabriel Friedman, and others.
  • Daily content from Financial Times, the world's leading global business publication.
  • Unlimited online access to read articles from Financial Post, National Post and 15 news sites across Canada with one account.
  • National Post ePaper, an electronic replica of the print edition to view on any device, share and comment on.
  • Daily puzzles, including the New York Times Crossword.

SUBSCRIBE TO UNLOCK MORE ARTICLES

Subscribe now to read the latest news in your city and across Canada.

  • Exclusive articles from Barbara Shecter, Joe O'Connor, Gabriel Friedman and others.
  • Daily content from Financial Times, the world's leading global business publication.
  • Unlimited online access to read articles from Financial Post, National Post and 15 news sites across Canada with one account.
  • National Post ePaper, an electronic replica of the print edition to view on any device, share and comment on.
  • Daily puzzles, including the New York Times Crossword.

REGISTER / SIGN IN TO UNLOCK MORE ARTICLES

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account.
  • Share your thoughts and join the conversation in the comments.
  • Enjoy additional articles per month.
  • Get email updates from your favourite authors.

THIS ARTICLE IS FREE TO READ REGISTER TO UNLOCK.

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account
  • Share your thoughts and join the conversation in the comments
  • Enjoy additional articles per month
  • Get email updates from your favourite authors

Sign In or Create an Account

or

Article content

In Santa Clara, California, where the world’s biggest supplier of artificial-intelligence chips is based, Digital Realty Trust Inc. applied in 2019 to build a data center. Roughly six years later, the development remains an empty shell awaiting full energization. Stack Infrastructure, which was acquired earlier this year by Blue Owl Capital Inc., has a nearby 48-megawatt project that’s also vacant, while the city-owned utility, Silicon Valley Power, struggles to upgrade its capacity.

Article content

Article content

Article content

The fate of the two facilities highlights a major challenge for the US tech sector and indeed the wider economy. While demand for data centers has never been greater, driven by the boom in cloud computing and AI, access to electricity is emerging as the biggest constraint. That’s largely because of aging power infrastructure, a slow build-out of new transmission lines and a variety of regulatory and permitting hurdles.

Article content

By signing up you consent to receive the above newsletter from Postmedia Network Inc.

Article content

And the pressure on power systems is only going to increase. Electricity requirements from AI computing will likely more than double in the US alone by 2035, based on BloombergNEF projections. Nvidia’s Jensen Huang and OpenAI’s Sam Altman are among corporate leaders that have predicted trillions of dollars will pour into building new AI infrastructure.

Article content

“The demand has never been higher, and it’s really a power-supply problem that we have,” Bill Dougherty, executive vice president for data center solutions at real estate brokerage CBRE Group Inc., said in an interview.

Article content

The Santa Clara projects are relatively small compared with the massive complexes for large-language model AI developers, which are now being built in Texas, Pennsylvania, Louisiana and New Mexico, where the cost of electricity is lower but the power sources are often still works in progress.  The smaller centers serve local cloud clients who pay a higher price for real estate and power to reduce latency caused by long-distance transmissions — think high-frequency traders or autonomous-vehicle operators who need information in microseconds. 

Article content

Article content

“There are portions of data-center demand that need to be as close as possible to population centers,” Dougherty said.  “That is the demand that needs to be in California. They can’t bring it online because there’s constraints on power.”

Article content

Santa Clara has 57 active or under construction data centers, according to a May city council presentation. Silicon Valley Power has agreements with Stack and Digital Realty that outline the terms and conditions for providing service, and it’s constantly evaluating requests for additional power, said utility spokesperson Janine de la Vega in an email.

Article content

“SVP is undertaking a $450 million system upgrade to meet the needs of these and other customers, and the project is currently on schedule to be completed in 2028,” she wrote.

Article content

There are other places, of course, facing similar delays due to utility-capacity limits. As the surge in demand outpaces the grid’s available power and transmission infrastructure, utilities across the US have struggled to keep up.

Article content

Last year, Dominion Energy Inc. said it expected the time it takes to connect large data centers to the grid to increase by one to three years, with some taking as long as seven years. Dominion serves northern Virginia’s so-called Data Center Alley, the world’s largest concentration of computing facilities. In Oregon, Amazon.com Inc. alleges it’s been denied sufficient power for four data centers by a Berkshire Hathaway Inc.-owned utility, according to a complaint.

Read Entire Article