Rio2 Provides Fenix Gold Mine Construction Update

5 hours ago 1

Article content

VANCOUVER, British Columbia, April 29, 2025 (GLOBE NEWSWIRE) — Rio2 Limited (“Rio2” or “the Company”) (TSXV: RIO; OTCQX: RIOFF; BVL: RIO) today provides an update on progress made at Rio2’s 100% owned Fenix Gold Project (“Fenix Gold” or “the
Project”) currently under construction in the Atacama Region, Chile. At the end of Q1 2025, construction was 19% complete and remains on track and on budget for first gold production in January 2026.

Financial Post

THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY

Subscribe now to read the latest news in your city and across Canada.

  • Exclusive articles from Barbara Shecter, Joe O'Connor, Gabriel Friedman, and others.
  • Daily content from Financial Times, the world's leading global business publication.
  • Unlimited online access to read articles from Financial Post, National Post and 15 news sites across Canada with one account.
  • National Post ePaper, an electronic replica of the print edition to view on any device, share and comment on.
  • Daily puzzles, including the New York Times Crossword.

SUBSCRIBE TO UNLOCK MORE ARTICLES

Subscribe now to read the latest news in your city and across Canada.

  • Exclusive articles from Barbara Shecter, Joe O'Connor, Gabriel Friedman and others.
  • Daily content from Financial Times, the world's leading global business publication.
  • Unlimited online access to read articles from Financial Post, National Post and 15 news sites across Canada with one account.
  • National Post ePaper, an electronic replica of the print edition to view on any device, share and comment on.
  • Daily puzzles, including the New York Times Crossword.

REGISTER / SIGN IN TO UNLOCK MORE ARTICLES

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account.
  • Share your thoughts and join the conversation in the comments.
  • Enjoy additional articles per month.
  • Get email updates from your favourite authors.

THIS ARTICLE IS FREE TO READ REGISTER TO UNLOCK.

Create an account or sign in to continue with your reading experience.

  • Access articles from across Canada with one account
  • Share your thoughts and join the conversation in the comments
  • Enjoy additional articles per month
  • Get email updates from your favourite authors

Sign In or Create an Account

or

Article content

Article content

Construction highlights for the five-month period from November 1, 2024, to March 31, 2025, are as follows, with all amounts expressed in US dollars:

Article content

Article content

Health & Safety – A total of 657,048 person-hours have been worked on the Project to date, with one Lost Time Incident for a finger injury, resulting in a Lost Time Incident Frequency Rate (LTIFR) of 1.52. The Total Incident Frequency Rate (TIFR) for the Project as at March 31, 2025, was 8.19.

Article content

By signing up you consent to receive the above newsletter from Postmedia Network Inc.

Article content

Budget – Total spend to date since October of $30.1 million for works completed, vs budget of $30.5 million. These costs exclude corporate overheads and do not include pre-construction costs expended in 2022.

Article content

Schedule – Total Project is currently 19% complete, and we expect to achieve first gold production in January 2026. All long lead time procurement items are in hand.

Article content

Construction Progress – Work was initiated on Critical Path Items such as access road upgrade, ADR plant, leach pad Phase 1 and PLS pond.

Article content

Human Resources – a total of 1,240 personnel (including contractors) are currently employed at the Project. 94% of the workforce is comprised of Chileans, with 41% of the workforce from the Atacama Region and 11% of the workforce female.

Article content

Article content

Exploration – Grade control drilling activities have commenced focused on the pit areas covering the first three years of future production.

Article content

VIRTUAL SITE IMAGERY AND PHOTOS

Article content

Updated 360-degree photography showing construction progress is available at the Company’s website at:

Article content

Article content

A progressive photographic history of construction activities and grade control drilling is available at:

Article content

Article content

Timetable and Next Steps

Article content

Upcoming key milestones include:

Article content

  • ADR plant building completed and closed in for winter – May
  • Completion of the PSL pond – April
  • Delivery of 10 ha of leach pad with over-liner material placed – May
  • Installation of the electrical switch rooms – May
  • Commissioning of the ADR Plant – November
  • Completion of Mine Expansion Study – December
  • First gold pour in January 2026
Read Entire Article