BRISBANE, Australia, Sept. 08, 2026 (GLOBE NEWSWIRE) — North American lithium producer Elevra Lithium Limited (“Elevra” or “Company”) (ASX:ELV; NASDAQ:ELVR) is pleased to announce the results of a Pre-Feasibility Study (“PFS”) for the staged North American Lithium (“NAL”) Brownfield Expansion in Québec. The PFS confirms the NAL Expansion as a high-value growth project that is expected to significantly increase annual spodumene concentrate production while reducing unit operating costs and generating attractive returns on capital invested.
THIS CONTENT IS RESERVED FOR SUBSCRIBERS ONLY
Subscribe now to read the latest news in your city and across Canada.
- Exclusive articles from Barbara Shecter, Joe O'Connor, Gabriel Friedman, and others.
- Daily content from Financial Times, the world's leading global business publication.
- Unlimited online access to read articles from Financial Post, National Post and 15 news sites across Canada with one account.
- National Post ePaper, an electronic replica of the print edition to view on any device, share and comment on.
- Daily puzzles, including the New York Times Crossword.
SUBSCRIBE TO UNLOCK MORE ARTICLES
Subscribe now to read the latest news in your city and across Canada.
- Exclusive articles from Barbara Shecter, Joe O'Connor, Gabriel Friedman and others.
- Daily content from Financial Times, the world's leading global business publication.
- Unlimited online access to read articles from Financial Post, National Post and 15 news sites across Canada with one account.
- National Post ePaper, an electronic replica of the print edition to view on any device, share and comment on.
- Daily puzzles, including the New York Times Crossword.
REGISTER / SIGN IN TO UNLOCK MORE ARTICLES
Create an account or sign in to continue with your reading experience.
- Access articles from across Canada with one account.
- Share your thoughts and join the conversation in the comments.
- Enjoy additional articles per month.
- Get email updates from your favourite authors.
THIS ARTICLE IS FREE TO READ REGISTER TO UNLOCK.
Create an account or sign in to continue with your reading experience.
- Access articles from across Canada with one account
- Share your thoughts and join the conversation in the comments
- Enjoy additional articles per month
- Get email updates from your favourite authors
Sign In or Create an Account
or
Article content
Article content
Highlights:
Article content
Article content
By signing up you consent to receive the above newsletter from Postmedia Network Inc.
Article content
- Consistent with the Updated NAL Expansion Scoping Study, the NAL Expansion will be delivered through a three-stage brownfield development, with Stage 1 increasing process plant throughput to the currently permitted rate of 4,500 tpd from mid-CY27, Stage 2 increasing milling capacity to 6,500 tpd from mid CY28, and Stage 3 delivering a permanent crushing solution aligned with increased milling capacity by mid CY29.
- On a post expansion basis, average annual spodumene concentrate production increases to 373 thousand tonnes per annum (ktpa) (nominal SC5.4, post ramp up), nearly double the no expansion scenario (“Base Case”) and 10% above the 338 ktpa estimate from May 20261. Production above the 338 ktpa capacity is attributable to improved mill feed grades largely due to benefits of ore sorting equipment.
- Life of mine (LOM) C1 cost of C$876/t (US$649/t)2 of spodumene concentrate, reducing to C$851/t (US$630/t)2 post-expansion with AISC of C$918/t (US$680/t)2.
- The NAL Expansion is fully funded based on the total initial CAPEX remaining unchanged at C$366M (US$271M)2 (AACE Class 4 estimate with a target accuracy range of ±40%), including C$73M (US$54M)2 of contingency, with Stage 1 CAPEX of C$92M (US$68M)2, Stage 2 CAPEX of C$101M (US$75M)2 and Stage 3 CAPEX of C$173M (US$128M) 2.
- NAL Expansion delivers a post-tax NPV (8%) of C$3,218M (US2,384M)2 , or an incremental post-tax NPV (8%) of C$943M (US$699M)2 compared to the C$969M (US$718M)2 incremental post-tax NPV (8%) declared in May 20261 due primarily to a 4% increase in the mining cost compared to the previous announcement following further detailed haulage modelling.
- The Company’s existing NAL Ore Reserves of 47.2Mt at 1.12% Li2O, comprising 0.2MT Proven and 47.0MT Probable Mineral Reserves, solely underpin the NAL Expansion production profile with a revised life of mine of 20 years.
- The PFS demonstrates that the NAL Expansion can increase production, reduce unit costs and generate significant incremental value from an existing operating asset and established infrastructure.
- The NAL Expansion is fully funded through Elevra’s Strategic Financing Package announced in May 20263.
Article content
Article content
_______________
1 ASX release “Updated NAL Expansion Scoping Study” dated 12 May 2026.
2 Figures converted from Canadian dollar to United States dollar at CAD/USD 1.35 as per the PFS.
3 ASX release “Transformational Financing Package to Accelerate Growth” dated 12 May 2026.
Article content
Elevra’s Chief Executive Officer and Managing Director, Mr Lucas Dow, said: “The NAL Expansion PFS confirms a compelling value proposition for Elevra, with a high-return brownfield expansion that materially increases production while reducing unit operating costs.
Article content
The ability to increase average annual production to 373,000 tonnes post-expansion, while reducing LOM average C1 unit costs post expansion to approximately C$851/t (US$630/t)4, demonstrates the significant operating leverage available at NAL. The production target and cost profile are underpinned by existing Ore Reserves and historical operating data, providing a strong foundation for the production and financial outcomes outlined in the PFS.
Article content
The staged development approach allows us to bring additional production online from mid-2027, by progressively increasing throughput and capturing operating efficiencies while managing project execution and prudent capital deployment.”
Advertisement 1
Advertisement 2
Article content
Study Confirms Compelling Economics for NAL Expansion
Article content
The PFS confirms a compelling economic case for the staged expansion of NAL, with the project expected to materially increase spodumene concentrate production while reducing unit operating costs and generating significant incremental value from an existing operating asset.
Article content
The PFS estimates an expansion-only post-tax NPV8% of C$943MM (US$699M)4, post-tax IRR of 49.9% and post-tax payback period of 34 months.
Article content
The expansion requires initial capital expenditure of C$366 M (US$271M)4, with total sustaining expenditure of C$527M (US$390M)4 over the expansion case. The financial analysis is unlevered and based on the Mineral Reserves estimated as part of the PFS.
Article content
The PFS establishes an average annual production rate of 348ktpa (5.4% Li₂O spodumene concentrate) and an average annual post-expansion production rate of 373ktpa (5.4% Li₂O spodumene concentrate).
Article content
Importantly, 100% of the Production Target is underpinned by Proven and Probable Ore Reserves. No Inferred Mineral Resources are included in the economic analysis or Production Target. The PFS states that the economic analysis was based on Measured and Indicated Mineral Resources only, with Inferred Mineral Resources excluded as too geologically speculative for mining and economic considerations to be applied.
Article content
Article content
Study Confirms Strong Operating Metrics for NAL Expansion
Article content
The PFS demonstrates significant operating leverage from increasing the scale of NAL’s existing operation.
Article content
Average annual post-expansion spodumene concentrate production is expected to increase from 199ktpa in the base case to 373ktpa post-expansion, while LOM average production increases from 196ktpa to 348ktpa.
Article content
LOM C1 operating costs are estimated at C$876/t (US$649/t)4 of concentrate, compared with C$1,048/t (US$776/t)4 for the base case, while the post-expansion C1 cost is estimated at C$851/t (US$630/t)4.
Article content
LOM AISC is estimated at C$954/t (US$707/t)4, reducing to C$918/t (US$680/t)4 post-expansion.
Article content
The PFS estimates total LOM operating expenditure of C$5.95B (US$4.41B)4 for the expansion case, with the cost estimates supported by actual NAL operating information including salaries, consumables, maintenance costs and established contracts.
Article content
_______________
4 Converted at CAD/USD 1.35.
Article content
Staged Expansion Delivery
Article content
The NAL Expansion Project has been designed as a three-stage brownfield development that progressively increases production and reduces unit costs while leveraging existing infrastructure.
Article content
Article content
Stage 1
Article content
Stage 1 is expected to deliver an initial 15-20% increase in annual spodumene concentrate production within NAL’s existing 4,500 tpd milling permit, together with a reduction in unit operating costs.
Article content
Stage 2
Article content
Stage 2 will expand downstream milling, flotation and filtration capacity to 6,500 tpd, with additional feed initially supported by a temporary mobile crushing circuit. Production from Stage 2 is expected to commence in mid CY28.
Article content
Stage 3
Article content
Stage 3 will replace the temporary and existing crushing circuits with a new crushing circuit capable of supporting the targeted 373ktpa post-expansion production profile, together with additional ore sorting capacity. Completion is expected in mid CY29.
Article content
The staged development approach was adopted to reduce execution risk, bring forward production growth and stage capital deployment.
Article content
Pre-Feasibility Study Metrics
Article content
Analysis of the financial model on the key economic assumptions indicates that the Project is robust in terms of operational and financial metrics. The Project is most sensitive to changes in commodity prices, exchange rates, head grades and recoveries, with the key Project assumptions and outputs shown in the tables below (please note that any reference to Base Case means NAL on an unexpanded or “as is” basis):
Article content
Table 1 – Main Financial Assumptions and Results Summary for the NAL Expansion Project
Article content
| Parameters | Unit | Base | May-26 Updated Scoping5 | PFS | ||||||
| Average Price 6% Li2O6 | USD$/t | $ | 2,260 | $ | 2,154 | $ | 2,137 | |||
| Life of mine (from FY27) | yrs | 35 | 21 | 20 | ||||||
| Total Waste | Mt | 336 | 335 | 336 | ||||||
| Total Ore Processed | Mt | 47 | 47 | 44 | ||||||
| Strip Ratio | – | 7.1 | 7.2 | 7.1 | ||||||
| Average Annual ROM | Mt/y | 1.36 | 2.22 | 2.41 | ||||||
| Average Feed Grade | % Li2O | 1.12 | % | 1.11 | % | 1.17 | % | |||
| LOM 5.4% Li2O Produced | Mt | 6.77 | 6.85 | 6.79 | ||||||
| Average Annual 5.4% Li2O Production (post expansion) | kt/y | 199 | 338 | 373 | ||||||
Article content
_______________
5 May-26 Scoping shows the results of the Updated Scoping Study for the NAL Expansion. See ASX release “Updated NAL Expansion Scoping Study” dated 12 May 2026.
6 Average Price 6% Li2O varies between the cases due to longer mine life at the long-term US$2,340 price for the base case.
Article content
Table 2 – Project Economics
Article content
| Project Economics | Unit | Base | May-26 Updated Scoping | PFS | ||
| LOM C1 Cost Concentrate | C$/t conc | 1,048 | 868 | 876 | ||
| LOM AISC | C$/t conc | 1,126 | 946 | 954 | ||
| LOM C1 Cost of Concentrate (post expansion) | C$/t conc | 1,045 | 847 | 851 | ||
| LOM AISC (post expansion) | C$/t conc | 1,112 | 922 | 918 | ||
| Total Sustaining Capital (SUSEX) | C$M | 512 | 526 | 527 | ||
| Total Initial CAPEX | C$M | – | 366 | 366 | ||
| NPV (8%) (post-tax) | C$M | 2,274 | 3,112 | 3,218 | ||
| IRR Expansion (post-tax) | % | – | 42 | % | 50 | % |
| Payback (post-tax) | Months | – | 25 | 34 | ||
Article content
Article content
Notes:
Article content
- All costs and sales are presented in constant 2026 CAD, with no inflation or escalation factors considered.
- $M = millions of dollars.
- The financial analysis was performed on existing Mineral Reserves as outlined in this report.
- The valuation calculations are unlevered.
- The average metallurgical recovery over the LOM is 71.2% for the expansion and 69.2% for the base case due to improvement in the flowsheet attributable to wet high-intensity magnetic separator (WHIMS) improvements.
- Plant availability is calculated at 90%.
- Tonnes of concentrate are presented as dry metric tonnes.
- An exchange rate of 1.35 CAD/USD was fixed over the LOM for the Project.
- The average 6% Li2O concentrate (SC6) price is based on a market analysis from Benchmark Mineral Intelligence for Q1 2026 as described in the market section and varies over the LOM from US$1,260/t to US$2,430/t.
- Average LOM SC6 pricing may vary between the cases due to longer mine life at the long term US$2,430 price for the base case (2036 and beyond).
- A discount rate of 8% was used for the base case and expansion scenarios.
- Net Cash Flow and valuation calculations include investment tax credit on CAPEX.
- The numbers have been rounded. Any discrepancy in the totals is due to rounding effects.
Article content
Article content
Purpose of this ASX Release
Article content
This ASX release provides readers with a bridge between prior ASX disclosure on 12 May 2026 “Updated NAL Expansion Scoping Study” and a National Instrument 43-101 Pre-Feasibility Study (appended) that has been prepared for compliance with Quebec, Canada regulatory requirements and to enable subsequent permitting activities for the NAL expansion. The NI43-101 report will also be available on SEDAR.
Article content
The company can confirm that the Resource and Reserve tables reproduced in this ASX release and the NI43-101 report are compliant with both ASX/JORC requirements and those related to NI43-101 reporting. It should also be noted the ore reserves: (1) are not being reported for the first time; or (2) are the same as those estimates which were previously reported in the FY26 Annual Report released to the ASX on 28 August 2026.
Article content
Mineral Resources and Ore Reserves
Article content
The project database contains data from 1,575 diamond drillholes surfaces and underground collared, spanning a total of 27,183 records of Li2O assays with a mean sample length of approximately 0.884 m. Li2O grade varies from 0.000% to 5.318%. Global average Li2O grade for raw samples (excluding 0.00% assays) is 0.783%. From this database, a subset of 562 surface collared drillholes totalling 153,047 m was used for the Mineral Resource estimate.
Article content
The current Mineral Resource Estimate and Ore Reserve Estimate are presented in Table 4 and Table 5 below. The Mineral Resource and Ore Reserve estimates were prepared by Competent Persons in accordance with the 2012 JORC Code.
Article content
Table 3 – North American Lithium – Mineral Resource Estimates (0.60% Li2O cut-off grade for the RPEEE pit and 0.70% Li2O cut-off grade for underground domain)
Article content
| Resource Classification | Method | Tonnes (Mt) | Li2O Grade (%) | Cut-Off Grade (%) |
| Indicated | Open Pit | 74.4 | 1.17 | 0.60 |
| Inferred | Open Pit | 8.6 | 1.13 | 0.60 |
| Indicated | Underground | – | – | – |
| Inferred | Underground | 10.3 | 1.01 | 0.70 |
| Total | 93.3 | 1.15 | ||
Article content
Table 4 – North American Lithium – Ore Reserves Estimate, as at of June 30, 2026
Article content
| Resource Classification | Tonnes (Mt) | Li2O Grade (%) | Cut-Off Grade (%) | Fe Grade (%) |
| Proved Ore Reserves | 0.2 | 0.93 | 0.60 | 1.48 |
| Probable Ore Reserves | 47.0 | 1.12 | 0.60 | 0.81 |
| Total | 47.2 | 1.12 | 0.60 | 0.81 |
Article content
The information on Mineral Resources and Ore Reserves is extracted from the announcement entitled “2026 Annual Report” published on the ASX on August 28th, 2026, and is available to view on the Elevra’s website on the ASX. The company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and, in the case of estimates of Mineral Resources or Ore Reserves, that all material assumptions and technical parameters underpinning the estimates in the relevant market announcement continue to apply and have not materially changed. The company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcement.
Article content
Article content
Background
Article content
The North American Lithium operation is a hard-rock lithium mining and concentration facility located in La Corne, within the Abitibi-Témiscamingue region of Quebec, Canada. The NAL facility was successfully restarted in March 2023, and the plant is currently permitted for 4,500 tpd of average annual milling rate.
Article content
The processing operation consists of three distinct processing areas:
Article content
- The primary, secondary and tertiary crushing, and ore sorting circuits to produce an upgraded plant feed for downstream processing.
- The spodumene processing plant including grinding, desliming, magnetic separation, flotation and dewatering circuits to produce a final spodumene concentrate.
- The process water and utilities circuits including tailings thickeners, reagents preparation, reverse osmosis treatment, and tailings management.
Article content
The objective of the NAL expansion project is to increase the plant’s milling throughput to an annual level of 6,500 tpd. Elevra determined that permitting is the critical path constraint and identified a project development sequence that provides a shorter timeframe to achieve increased production from NAL. The additional new permitting information, combined with existing permits, provides a pathway to stage the expansion of production volumes at NAL in a disciplined, agile and more time efficient manner.
Article content
Article content
The expansion pathway is now proposed to take the form of a series of debottlenecking steps which are expected to:
Article content
- Increase production capacity above current levels in a staged and incremental manner;
- Improve plant recovery by the introduction of additional LIMS and WHIMS, and additional flotation conditioning capacity;
- Reduce the timeframe to achieve the expanded average annual production volume of 373ktpa of spodumene concentrate; and
- Enable the capital investment to be staged and, in doing so, reduce the initial upfront capital requirements.
Article content
The debottlenecking steps are anticipated to be delivered as below:
Article content
- An initial 15-20% increase in annual spodumene concentrate production above current production levels commencing in mid-CY27 with an incremental reduction in unit operating costs. This increase is within the current limits of the milling permit, which is set at 4,500 tpd;
- A subsequent expansion of the milling, flotation and filtration capacity to 6,500 tpd. The incremental feed material will be processed using a temporary mobile crushing circuit operating in conjunction with the existing crushing circuit. The further expanded production is expected to commence mid CY28, with an additional incremental reduction in unit operating costs; and
- The replacement of the temporary mobile crushing circuit and the existing crushing circuit with a new crushing circuit capable of meeting feed requirements for a LOM average production of 373 ktpa post-expansion. This final step will include additional ore sorting capacity and is expected to be completed in mid CY29 delivering crushing cost efficiencies which are required to meet the anticipated LOM cost reduction.
Article content
Announcement authorised for release by Elevra’s Managing Director and Chief Executive Officer.
Article content
About Elevra Mining
Article content
Elevra Lithium Limited is a North American lithium producer (ASX:ELV; NASDAQ:ELVR) with projects in Québec, Canada, United States and a joint venture in Western Australia.
Article content
Elevra’s assets comprise North American Lithium (100%), a 60% stake in the Moblan Lithium Project in Central Québec and the Carolina Lithium project (100%) in the United States7.
Article content
For more information, please visit us at www.elevra.com.
Article content
Competent Person’s Statement
Article content
The information on Mineral Resources and Ore Reserves are extracted from the announcement entitled “2026 Annual Report” published on the ASX on 28th August 2026 and is available to view on the Elevra’s website or on the ASX. The Company confirms that it is not aware of any new information or data that materially affects the information included in the original market announcement and all material assumptions and technical parameters continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcements
Article content
Article content
The ASX release dated 28th August 2026 that relates to Mineral Resources for the NAL project – referred to in this announcement – is based on and fairly represents information compiled by Mr Stephen John Andrew, an independent consultant employed by Measured Group and who is a member of the Australasian Institute of Mining and Metallurgy (AusIMM). Mr Andrews has sufficient experience which is relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as a Competent Person as defined in the JORC Code (2012 Edition) of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves.” The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcements
Article content
The information in this announcement and the ASX release dated 28th August 2026 relating to Ore Reserves for the North American Lithium project is based on, and fairly represents, information and supporting documentation prepared by Mr. Tony O’Connell an independent consultant employed by Optimal Mining Solutions Pty Ltd and is a member of the Australasian Institute of Mining and Metallurgy (AusIMM). Mr O’Connell has sufficient experience which is relevant to the type of deposits and mining method under consideration and to the activity which has been undertaken to qualify as a Competent Person as defined in the 2012 Edition of the “Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves”. The Company confirms that the form and context in which the Competent Person’s findings are presented have not been materially modified from the original market announcements.
Article content
Article content
Forward Looking Statements
Article content
This press release contains certain forward-looking statements. Such statements include, but are not limited to, statements relating to “reserves” or “resources”. Forward-looking statements are based on certain assumptions and involve known and unknown risks, uncertainties and other factors, many of which are beyond Elevra’s control. Actual events or results may differ materially from the events or results expressed or implied in any forward-looking statement. There can be no assurance that such information will prove to be accurate as actual results and future events could differ materially from those anticipated in such forward-looking statements.
Article content
_______________
7 See ASX release dated 11 May 2026, “Elevra enters agreement to sell Ewoyaa Project Interest”.
Article content
Cautionary Statements
Article content
The Pre-Feasibility Study (“PFS”) discussed in this announcement has been undertaken to assess the technical and economic viability of the brownfield expansion of the existing North American Lithium (“NAL”) operation. The PFS is a comprehensive technical and economic study of the expansion project and includes a financial analysis based on reasonable assumptions regarding the applicable Modifying Factors and other relevant factors. The PFS has been prepared to a level of confidence sufficient to support the assessment of technical and economic viability and the estimation of Ore Reserves, as applicable. A PFS is, however, at a lower level of confidence than a Feasibility Study and the estimates and assumptions contained in the PFS remain subject to further refinement through subsequent engineering, design and project execution activities.
Article content
The PFS has provided Pre-Feasibility Study level estimates of production, capital and operating costs and financial returns. The production target and forecast financial information included in the PFS are based solely on the current NAL Ore Reserves reported in Elevra Lithium Limited’s 2026 Annual Report released to ASX on 28 August 2026. No Inferred Mineral Resources or Exploration Targets are included in the production target or the economic analysis underpinning the PFS.
Article content
The PFS is based on the material assumptions outlined in [this announcement] / [attached PFS], including assumptions regarding production rates, metallurgical recoveries, capital and operating costs, commodity prices, foreign exchange rates, permitting, project schedule and other applicable Modifying Factors. While Elevra considers that the material assumptions used in the PFS have a reasonable basis, actual results may differ materially from those anticipated in the PFS and there is no certainty that the assumptions will prove to be correct or that the outcomes indicated by the PFS will be achieved.
Article content
Article content
Based on the Company’s current cost estimates and existing funding arrangements, Elevra considers the NAL Expansion to be fully funded. However, there can be no assurance that actual project costs will not exceed current estimates or that delays, changes in project scope, permitting requirements, market conditions or other circumstances will not result in additional funding requirements.
Article content
This announcement contains forward-looking statements, including statements concerning production targets, production rates, mine life, metallurgical recoveries, capital and operating costs, project timing, commodity prices, financial performance and other economic outcomes. These forward-looking statements are based on assumptions and expectations which Elevra considers reasonable as at the date of this announcement. However, forward-looking statements are subject to known and unknown risks, uncertainties and other factors, many of which are outside Elevra’s control, which may cause actual results, performance or achievements to differ materially from those expressed or implied by those statements.
Article content
Given the uncertainties associated with forward-looking information and the fact that a PFS is at a lower level of confidence than a Feasibility Study, investors are cautioned not to place undue reliance on the PFS, the production target, forecast financial information or other forward-looking statements contained in this announcement.
Article content
For more information, please contact:
Article content
Andrew Barber
Article content
Investor Relations
Article content
Ph: +617 3369 7058
Article content
Article content
Article content
Article content

Article content
Article content

1 hour ago
2
English (US)