B2Gold Reports Q2 2025 Results

2 hours ago 3

Article content

The Gramalote Project will continue to advance resettlement programs, establish coexistence programs for small miners, work on health, safety and environmental projects and continue to work with the government and local communities on social programs.

Article content

Outlook

Article content

The Company is pleased with its positive second quarter of 2025 operating and financial results. The Company is on track to meet its 2025 total gold production guidance of between 970,000 and 1,075,000 ounces. The Fekola Complex, Masbate Mine, and Otjikoto Mine continue to outperform production expectations and on June 30, 2025 the Company completed the first gold pour from its new Goose Mine in Nunavut. The Goose Mine is expected to ramp up quickly and achieve commercial production in September 2025 and contribute between 120,000 and 150,000 ounces of gold in 2025. Looking forward, over the first six full calendar years of operation from 2026 to 2031 inclusive, the Goose Mine is estimated to contribute average annual gold production of approximately 300,000 ounces of gold per year, based only on existing Mineral Reserves.

Article content

Article content

The price of gold realized per ounce continues to significantly exceed the original 2025 budgeted gold price of $2,250 per ounce, enhancing the Company’s cash generating activities. The Company remains in a strong financial position and is well placed to complete its budgeted capital and exploration activities for 2025, manage its financial commitments and continue to pay a dividend with a yield that puts the Company at the higher end of its peer group.

Article content

The Company has updated its consolidated cash cost guidance range to reflect the expected impact of lower than estimated fuel costs in 2025 and forecast results from the Goose Mine in the second half of 2025. Consolidated cash operating cost guidance for the Fekola Complex, Masbate Mine and Otjikoto Mine for 2025 is now forecast to be between $740 and $800 per gold ounce (lower than the previous guidance range of between $835 and $895 per gold ounce). With the inclusion of the post-commercial production estimates for the Goose Mine (commercial production expected in September 2025), consolidated cash operating cost guidance is now forecast to be between $795 and $855 per ounce. Consolidated all-in sustaining cost guidance for the Fekola Complex, Masbate Mine and Otjikoto Mine for 2025 remain unchanged, with a guidance range of between $1,460 and $1,520 per ounce. With the inclusion of the post-commercial production estimates for the Goose Mine (commercial production expected in September 2025), consolidated all-in sustaining cost guidance is forecast to be between $1,490 and $1,550 per ounce sold.

Article content

The Company has made significant progress in the development and enhancement of existing operations, which continues to be an area of focus. The recent approval for commencement of mining activities at Fekola underground demonstrates the ongoing commitment of both the Company and the State of Mali to implement the matters laid out in the Memorandum of Understanding (the “MOU”) entered into in September 2024. Our next key milestone under the MOU is the receipt of an exploitation permit for Fekola Regional which is expected prior to the end of the third quarter of 2025.

Article content

At the Goose Mine, the Company is pursuing multiple optimization studies, including one study to analyze the potential to increase mill throughput from 4,000 tpd potentially up to 6,000 tpd, and a separate study analyzing the implementation of a flotation / concentrate leach process which has the potential to increase gold recovery and reduce processing unit costs. The Goose Mine is currently permitted for mill throughput of up to 6,000 tpd, so no amendment to the Project Certificate would be required if the Company pursues the mill throughput expansion. The results of these studies are expected to be finalized in late 2025 / early 2026. Once the studies are completed, the Company will evaluate the economics of each option and pursue the desired choice.

Article content

In Namibia and based on the positive PEA results for the Antelope deposit at the Otjikoto Mine released in February 2025, B2Gold believes that the Antelope deposit has the potential to become a small-scale, low-cost underground gold mine that can supplement the low-grade stockpile production during the period from 2028 to 2032 and result in meaningful production profile for Otjikoto into the next decade.

Article content

We continue to assess development opportunities and projects where we can deploy our proven internal mine construction team. Development opportunities being assessed include our 100% owned Gramalote Project. The Company recently completed a feasibility study for the Gramalote Project in Colombia which demonstrated positive economics. The feasibility study included modifications to the processing plant and infrastructure locations and therefore a Modified Work Plan and Modified Environmental Impact Study will also be required. Work on the modifications to the work plan and environmental study are well advanced and the Company expects them to be completed and submitted in the near-future. Assessment of the Gramalote Project remains ongoing and any construction decision is not expected until late 2026 or early 2027.

Article content

Exploration also remains a key focus as B2Gold seeks to both expand its mineral reserve and mineral resource base at its existing operations as well as seeking out greenfield opportunities, including strategic investments in prospective junior exploration companies.

Article content

The Company’s ongoing strategy is to continue to maximize responsible profitable production from its existing mines, maintain a strong financial position, realize the potential increase in gold production from the Company’s existing development projects, continue exploration programs across the Company’s robust land packages, evaluate new exploration, development and production opportunities and continue to return capital to shareholders.

Article content

Mary-Lynn Oke, CPA, Appointed to B2Gold’s Board of Directors

Article content

On August 6, 2025, Mary-Lynn Oke was appointed to B2Gold’s Board of Directors.

Article content

Kelvin Dushnisky, Chair of the Board of B2Gold, commented, “On behalf of the Board, we are delighted to welcome Mary-Lynn Oke to the B2Gold Board. Mary-Lynn’s extensive experience in financial management and deep understanding of the mining sector will be a valuable asset as the Company continues to execute on its long-term strategic objectives.”

Article content

Mary-Lynn Oke has over 25 years of experience spanning corporate finance, taxation, treasury, and senior leadership roles. Ms. Oke was previously with Hudbay Minerals Inc., where she was the Vice President, Finance Global Operations and the Chief Financial Officer for its Canadian Business Operations. Ms. Oke currently serves on the Boards of Directors of NexGold Mining Corp. and Jaguar Mining Inc. In addition to her board roles, Ms. Oke provides senior financial and strategic advisory services to organizations, helping them enhance operational efficiency and business performance. Ms. Oke holds an Honours Bachelor of Arts in Business Administration from the Richard Ivey School of Business and is a Chartered Professional Accountant.

Article content

Second Quarter 2025 Financial Results – Conference Call Details

Article content

B2Gold executives will host a conference call to discuss the results on Friday, August 8, 2025, at 8:00 am PT / 11:00 am ET.

Article content

Participants may register for the conference call here: registration link. Upon registering, participants will receive a calendar invitation by email with dial in details and a unique PIN. This will allow participants to bypass the operator queue and connect directly to the conference. Registration will remain open until the end of the conference call. Participants may also dial in using the numbers below:

Article content

  • Toll-free in U.S. and Canada: +1 (833)-821-2803
  • All other callers: +1 (647)-846-2419

Article content

The conference call will be available for playback for two weeks by dialing toll-free in the U.S. and Canada: +1 (855)-669-9658, replay access code 1475370. All other callers: +1 (412)-317-0088, replay access code 1475370.

Article content

About B2Gold

Article content

B2Gold is a responsible international senior gold producer headquartered in Vancouver, Canada. Founded in 2007, today, B2Gold has operating gold mines in Canada, Mali, Namibia and the Philippines, and numerous development and exploration projects in various countries. B2Gold forecasts gold production of between 970,000 and 1,075,000 ounces in 2025.

Article content

Qualified Persons

Article content

Bill Lytle, Senior Vice President and Chief Operating Officer, a qualified person under NI 43-101, has approved the scientific and technical information related to operations matters contained in this news release.

Article content

Andrew Brown, P. Geo., Vice President, Exploration, a qualified person under NI 43-101, has approved the scientific and technical information related to exploration and mineral resource matters contained in this news release.

Article content

ON BEHALF OF B2GOLD CORP.

Article content

“Clive T. Johnson”
President and Chief Executive Officer

Article content

Source: B2Gold Corp.

Article content

The Toronto Stock Exchange and NYSE American LLC neither approve nor disapprove the information contained in this news release.

Article content

Production results and production guidance presented in this news release reflect the total production at the mines B2Gold operates on a 100% basis. Please see our most recent Annual Information Form for a discussion of our ownership interest in the mines B2Gold operates.

Article content

This news release includes certain “forward-looking information” and “forward-looking statements” (collectively “forward-looking statements”) within the meaning of applicable Canadian and United States securities legislation, including: projections; outlook; guidance; forecasts; estimates; and other statements regarding future or estimated financial and operational performance, gold production and sales, revenues and cash flows, and capital costs (sustaining and non-sustaining) and operating costs, including projected cash operating costs and all-in sustaining costs, and budgets on a consolidated and mine by mine basis, which if they occur, would have on our business, our planned capital and exploration expenditures; future or estimated mine life, metal price assumptions, ore grades or sources, gold recovery rates, stripping ratios, throughput, ore processing; statements regarding anticipated exploration, drilling, development, construction, permitting and other activities or achievements of B2Gold; and including, without limitation: remaining well positioned for continued strong operational and financial performance in 2025; projected gold production, cash operating costs and all-in sustaining costs (on a consolidated and mine by mine basis in 2025 for the Fekola Complex, the Otjikoto Mine, the Masbate Gold Project and the Goose Mine; total consolidated gold production of between 970,000 and 1,075,000 ounces in 2025, with cash operating costs of between $740 and $800 per gold ounce ($795 and $855 per gold ounce when including the post-commercial production estimates for the Goose Mine in the guidance range) and all-in sustaining cost guidance of between $1,460 and $1,520 per gold ounce ($1,490 and $1,550 per gold ounce when including the post-commercial production estimates for the Goose Mine in the guidance range); continued prioritization of developing the Goose Mine in a manner that recognizes Indigenous input and concerns and brings long-term socio-economic benefits to the area; the Goose Mine producing between 120,000 and 150,000 ounces in 2025 and approximately 300,000 ounces of gold per year for the first full six years of production; the potential ramp-up to commercial production by the end of the third quarter of 2025; the commencement of high-grade stope ore production at Umwelt underground development in the third quarter of 2025; Fekola underground contributing between 25,000 to 35,000 ounces of gold production in 2025, ramping up significantly in 2026 and subsequent years; the receipt of the exploitation permit for Fekola Regional and Fekola Regional production expected to commence prior to the end of the third quarter of 2025; Fekola Regional contributing approximately 180,000 ounces of additional annual gold production in its first four full years of production from 2026 through 2029, with a mine life expected to extend well into the 2030’s; the potential for the Antelope deposit to be developed as an underground operation and contribute up to 65,000 per year during the low-grade stockpile processing in 2029 through 2032 and the Otjikoto Mine producing an average of approximately 110,000 ounces per year during that period;; the potential to develop the Gramalote Project as an open pit gold mine; the ability to deliver 22,064 ounces per month for the 12-month period from July 2025 to June 2026 to satisfy delivery of the total Gold Prepay obligation of 264,768 ounces in full; planned 2025 exploration budgets for Canada, Mali, Namibia, the Philippines and Kazakhstan and other grassroots projects; and the potential payment of future dividends, including the timing and amount of any such dividends, and the expectation that quarterly dividends will be maintained at the same level. All statements in this news release that address events or developments that we expect to occur in the future are forward-looking statements. Forward-looking statements are statements that are not historical facts and are generally, although not always, identified by words such as “expect”, “plan”, “anticipate”, “project”, “target”, “potential”, “schedule”, “forecast”, “budget”, “estimate”, “intend” or “believe” and similar expressions or their negative connotations, or that events or conditions “will”, “would”, “may”, “could”, “should” or “might” occur. All such forward-looking statements are based on the opinions and estimates of management as of the date such statements are made.

Article content

Forward-looking statements necessarily involve assumptions, risks and uncertainties, certain of which are beyond B2Gold’s control, including risks associated with or related to: the volatility of metal prices and B2Gold’s common shares; changes in tax laws; the dangers inherent in exploration, development and mining activities; the uncertainty of mineral reserve and resource estimates; not achieving production, cost or other estimates; actual production, development plans and costs differing materially from the estimates in B2Gold’s feasibility and other studies; the ability to obtain and maintain any necessary permits, consents or authorizations required for mining activities; environmental regulations or hazards and compliance with complex regulations associated with mining activities; climate change and climate change regulations; the ability to replace mineral reserves and identify acquisition opportunities; the unknown liabilities of companies acquired by B2Gold; the ability to successfully integrate new acquisitions; fluctuations in exchange rates; the availability of financing; financing and debt activities, including potential restrictions imposed on B2Gold’s operations as a result thereof and the ability to generate sufficient cash flows; operations in foreign and developing countries and the compliance with foreign laws, including those associated with operations in Mali, Namibia, the Philippines and Colombia and including risks related to changes in foreign laws and changing policies related to mining and local ownership requirements or resource nationalization generally; remote operations and the availability of adequate infrastructure; fluctuations in price and availability of energy and other inputs necessary for mining operations; shortages or cost increases in necessary equipment, supplies and labour; regulatory, political and country risks, including local instability or acts of terrorism and the effects thereof; the reliance upon contractors, third parties and joint venture partners; the lack of sole decision-making authority related to Filminera Resources Corporation, which owns the Masbate Gold Project; challenges to title or surface rights; the dependence on key personnel and the ability to attract and retain skilled personnel; the risk of an uninsurable or uninsured loss; adverse climate and weather conditions; litigation risk; competition with other mining companies; community support for B2Gold’s operations, including risks related to strikes and the halting of such operations from time to time; conflicts with small scale miners; failures of information systems or information security threats; the ability to maintain adequate internal controls over financial reporting as required by law, including Section 404 of the Sarbanes-Oxley Act; compliance with anti-corruption laws, and sanctions or other similar measures; social media and B2Gold’s reputation; as well as other factors identified and as described in more detail under the heading “Risk Factors” in B2Gold’s most recent Annual Information Form, B2Gold’s current Form 40-F Annual Report and B2Gold’s other filings with Canadian securities regulators and the U.S. Securities and Exchange Commission (the “SEC”), which may be viewed at www.sedarplus.ca and www.sec.gov, respectively (the “Websites”). The list is not exhaustive of the factors that may affect B2Gold’s forward-looking statements.

Article content

B2Gold’s forward-looking statements are based on the applicable assumptions and factors management considers reasonable as of the date hereof, based on the information available to management at such time. These assumptions and factors include, but are not limited to, assumptions and factors related to B2Gold’s ability to carry on current and future operations, including: development and exploration activities; the timing, extent, duration and economic viability of such operations, including any mineral resources or reserves identified thereby; the accuracy and reliability of estimates, projections, forecasts, studies and assessments; B2Gold’s ability to meet or achieve estimates, projections and forecasts; the availability and cost of inputs; the price and market for outputs, including gold; foreign exchange rates; taxation levels; the timely receipt of necessary approvals or permits; the ability to meet current and future obligations; the ability to obtain timely financing on reasonable terms when required; the current and future social, economic and political conditions; and other assumptions and factors generally associated with the mining industry.

Article content

B2Gold’s forward-looking statements are based on the opinions and estimates of management and reflect their current expectations regarding future events and operating performance and speak only as of the date hereof. B2Gold does not assume any obligation to update forward-looking statements if circumstances or management’s beliefs, expectations or opinions should change other than as required by applicable law. There can be no assurance that forward-looking statements will prove to be accurate, and actual results, performance or achievements could differ materially from those expressed in, or implied by, these forward-looking statements. Accordingly, no assurance can be given that any events anticipated by the forward-looking statements will transpire or occur, or if any of them do, what benefits or liabilities B2Gold will derive therefrom. For the reasons set forth above, undue reliance should not be placed on forward-looking statements.

Article content

The projected range of all-in sustaining costs includes sustaining capital expenditures, corporate administrative expense, mine-site exploration and evaluation costs and reclamation cost accretion, and exclude the effects of expansionary capital and non-sustaining expenditures. Projected GAAP total production cash costs for the full year would require inclusion of the projected impact of future included and excluded items, including items that are not currently determinable, but may be significant, such as sustaining capital expenditures, reclamation cost accretion. Due to the uncertainty of the likelihood, amount and timing of any such items, B2Gold does not have information available to provide a quantitative reconciliation of projected all-in sustaining costs to a total production cash costs projection. B2Gold believes that this measure represents the total costs of producing gold from current operations, and provides B2Gold and other stakeholders of the Company with additional information of B2Gold’s operational performance and ability to generate cash flows. All-in sustaining costs, as a key performance measure, allows B2Gold to assess its ability to support capital expenditures and to sustain future production from the generation of operating cash flows. This information provides management with the ability to more actively manage capital programs and to make more prudent capital investment decisions.

Article content

Non-IFRS Measures

Article content

This news release includes certain terms or performance measures commonly used in the mining industry that are not defined under International Financial Reporting Standards (“IFRS”), including “cash operating costs” and “all-in sustaining costs” (or “AISC”). Non-IFRS measures do not have any standardized meaning prescribed under IFRS, and therefore they may not be comparable to similar measures employed by other companies. The projected range of AISC is anticipated to be adjusted to include sustaining capital expenditures, corporate administrative expense, mine-site exploration and evaluation costs and reclamation cost accretion and amortization, and exclude the effects of expansionary capital and non-sustaining expenditures. Projected GAAP total production cash costs for the full year would require inclusion of the projected impact of future included and excluded items, including items that are not currently determinable, but may be significant, such as sustaining capital expenditures, reclamation cost accretion and amortization. Due to the uncertainty of the likelihood, amount and timing of any such items, B2Gold does not have information available to provide a quantitative reconciliation of projected AISC to a total production cash costs projection. B2Gold believes that this measure represents the total costs of producing gold from current operations, and provides B2Gold and other stakeholders of the Company with additional information of B2Gold’s operational performance and ability to generate cash flows. AISC, as a key performance measure, allows B2Gold to assess its ability to support capital expenditures and to sustain future production from the generation of operating cash flows. This information provides management with the ability to more actively manage capital programs and to make more prudent capital investment decisions.

Article content

The data presented is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS and should be read in conjunction with B2Gold’s consolidated financial statements. Readers should refer to B2Gold’s Management Discussion and Analysis, available on the Websites, under the heading “Non-IFRS Measures” for a more detailed discussion of how B2Gold calculates certain such measures and a reconciliation of certain measures to IFRS terms.

Article content

Cautionary Statement Regarding Mineral Reserve and Resource Estimates

Article content

The disclosure in this news release was prepared in accordance with Canadian standards for the reporting of mineral resource and mineral reserve estimates, which differ in some material respects from the disclosure requirements of United States securities laws. In particular, and without limiting the generality of the foregoing, the terms “mineral reserve”, “proven mineral reserve”, “probable mineral reserve”, “inferred mineral resources,”, “indicated mineral resources,” “measured mineral resources” and “mineral resources” used or referenced in this news release are Canadian mineral disclosure terms as defined in accordance with Canadian National Instrument 43-101 – Standards of Disclosure for Mineral Projects (“NI 43-101”) and the Canadian Institute of Mining, Metallurgy and Petroleum (the “CIM”) – CIM Definition Standards on Mineral Resources and Mineral Reserves, adopted by the CIM Council, as amended (the “CIM Definition Standards”). The definitions of these terms, and other mining terms and disclosures, differ from the definitions of such terms, if any, for purposes of the SEC’s disclosure rules for domestic United State issuers. As a foreign private issuer that is eligible to file reports with the SEC pursuant to the MJDS, B2Gold is not required to provide disclosure on its mineral properties under applicable SEC rules and regulations and provides disclosure under NI 43-101 and the CIM Definition Standards. Accordingly, mineral reserve and mineral resource information and other technical information contained in this news release may not be comparable to similar information disclosed by companies subject to the SEC’s reporting and disclosure requirements for domestic United States issuers.

Article content

Mineral resources that are not mineral reserves do not have demonstrated economic viability. Due to the uncertainty of measured, indicated or inferred mineral resources, these mineral resources may never be upgraded to proven and probable mineral reserves. Investors are cautioned not to assume that any part of mineral deposits in these categories will ever be converted into reserves or recovered. In addition, United States investors are cautioned not to assume that any part or all of B2Gold’s measured, indicated or inferred mineral resources constitute or will be converted into mineral reserves or are or will be economically or legally mineable without additional work.

Article content

Historical results or feasibility models presented herein are not guarantees or expectations of future performance. Mineral resources that are not mineral reserves do not have demonstrated economic viability. Due to the uncertainty of measured, indicated or inferred mineral resources, these mineral resources may never be upgraded to proven and probable mineral reserves. Investors are cautioned not to assume that any part of mineral deposits in these categories will ever be converted into reserves or recovered. In addition, United States investors are cautioned not to assume that any part or all of B2Gold’s measured, indicated or inferred mineral resources constitute or will be converted into mineral reserves or are or will be economically or legally mineable without additional work.

Article content

B2GOLD CORP.
CONDENSED INTERIM CONSOLIDATED STATEMENTS OF OPERATIONS
FOR THE THREE AND SIX MONTHS ENDED JUNE 30
(Expressed in thousands of United States dollars, except per share amounts)
(Unaudited)
 
  For the three
months ended
June 30, 2025
 For the three
months ended
June 30, 2024
 For the six
months ended
June 30, 2025
 For the six
months ended
June 30, 2024
         
Gold revenue $692,206  $492,569  $1,224,313  $954,013 
         
Cost of sales        
Production costs  (160,363)  (151,299)  (322,357)  (308,044)
Depreciation and depletion  (102,705)  (95,008)  (192,262)  (185,454)
Royalties and production taxes  (77,701)  (33,089)  (120,507)  (63,116)
Total cost of sales  (340,769)  (279,396)  (635,126)  (556,614)
         
Gross profit  351,437   213,173   589,187   397,399 
         
General and administrative  (15,783)  (12,968)  (27,585)  (27,106)
Share-based payments  (8,134)  (4,792)  (14,003)  (9,746)
Non-recoverable input taxes  (5,431)  (2,695)  (12,277)  (6,999)
Write-down of mining interests     (636)  (5,118)  (636)
Foreign exchange gains (losses)  12,781   (11,356)  19,995   (13,735)
Community relations  (559)  (442)  (1,558)  (931)
Share of net (loss) income of associates  (576)  2,582   178   4,679 
Impairment of long-lived assets     (215,216)     (215,216)
Gain on sale of mining interests     48,662      48,662 
Gain on sale of shares in associate     16,822      16,822 
Other expense  (4,219)  (2,322)  (10,470)  (7,754)
Operating income  329,516   30,812   538,349   185,439 
         
(Losses) gains on derivative instruments  (21,153)  429   (64,472)  704 
Change in fair value of gold stream  (21,754)  (8,387)  (52,306)  (19,239)
Interest and financing expense  (4,854)  (7,465)  (10,577)  (17,036)
Interest income  2,913   7,671   6,085   13,126 
Gain (loss) on dilution of associate     998      (8,984)
Other income  1,729   12   2,085   155 
Income from operations before taxes  286,397   24,070   419,164   154,165 
         
Current income tax, withholding and other taxes  (160,174)  (96,697)  (246,257)  (158,281)
Deferred income tax recovery  34,530   37,850   50,410   17,820 
Net income (loss) for the period $160,753  $(34,777) $223,317  $13,704 
         
Attributable to:        
Shareholders of the Company $154,424  $(24,004) $212,011  $15,747 
Non-controlling interests  6,329   (10,773)  11,306   (2,043)
Net income (loss) for the period $160,753  $(34,777) $223,317  $13,704 
         
Earnings (loss) per share (attributable to shareholders of the Company)        
Basic $0.12  $(0.02) $0.16  $0.01 
Diluted $0.10  $(0.02) $0.14  $0.01 
         
Weighted average number of common shares outstanding (in thousands)        
Basic  1,321,740   1,307,176   1,320,074   1,305,183 
Diluted  1,477,021   1,307,176   1,473,509   1,308,746 
 

Article content

B2GOLD CORP.
CONDENSED INTERIM CONSOLIDATED STATEMENTS OF CASH FLOWS
FOR THE THREE AND SIX MONTHS ENDED JUNE 30
(Expressed in thousands of United States dollars)
(Unaudited)
 
  For the three
months ended
June 30, 2025
 For the three
months ended
June 30, 2024
 For the six
months ended
June 30, 2025
 For the six
months ended
June 30, 2024
Operating activities        
Net income (loss) for the period $160,753  $(34,777) $223,317  $13,704 
Mine restoration provisions settled  (607)  (650)  (1,100)  (941)
Non-cash charges, net  140,770   231,149   322,693   384,914 
Proceeds from prepaid sales           500,023 
Changes in non-cash working capital  28,862   (79,709)  14,022   (57,724)
Changes in long-term inventory  (30,326)  (17,405)  (41,283)  (15,696)
Changes in long-term value added tax receivables  (44,371)  (36,176)  (83,780)  (51,121)
Cash provided by operating activities  255,081   62,432   433,869   773,159 
         
Financing activities        
Proceeds from convertible senior unsecured notes, net of financing costs        445,913    
Repayment of revolving credit facility        (400,000)  (150,000)
Equipment loan facility draw downs  3,314      12,304    
Repayment of equipment loan facilities  (4,155)  (3,519)  (8,557)  (5,906)
Interest and commitment fees paid  (1,148)  (1,090)  (4,642)  (4,669)
Cash proceeds from stock option exercises  3,936   1,357   6,167   2,445 
Dividends paid  (25,959)  (45,869)  (51,511)  (91,858)
Principal payments on lease arrangements  (8,441)  (1,140)  (11,413)  (2,588)
Distributions to non-controlling interests  (9,435)  (2,708)  (17,617)  (7,288)
Other  (4)  691   (4,271)  962 
Cash used by financing activities  (41,892)  (52,278)  (33,627)  (258,902)
         
Investing activities        
Expenditures on mining interests:        
Fekola Mine  (53,379)  (53,179)  (117,382)  (133,741)
Masbate Mine  (17,499)  (6,507)  (25,232)  (15,037)
Otjikoto Mine  (4,709)  (11,706)  (8,316)  (25,519)
Goose Mine  (143,484)  (127,704)  (238,296)  (245,155)
Fekola Regional Properties  (5,004)  (4,924)  (8,173)  (9,425)
Gramalote Project  (5,151)  (3,560)  (11,944)  (6,870)
Other exploration  (13,878)  (11,572)  (19,474)  (20,412)
Redemption of short-term investments  22,544      22,544    
Purchase of short-term investments  (4,854)     (10,926)   
Funding of reclamation accounts  (5,027)  (1,676)  (6,448)  (2,705)
Purchase of shares in associate  (4,800)     (4,800)   
Purchase of long-term investments  (1,318)  (6,252)  (3,126)  (6,252)
Cash proceeds on sale of investment in associate     100,302      100,302 
Cash proceeds on sale of long-term investment     18,661      18,661 
Other  117   (295)  55   (1,836)
Cash used by investing activities  (236,442)  (108,412)  (431,518)  (347,989)
         
(Decrease) increase in cash and cash equivalents  (23,253)  (98,258)  (31,276)  166,268 
         
Effect of exchange rate changes on cash and cash equivalents  1,621   (2,716)  2,796   (6,323)
Cash and cash equivalents, beginning of period  330,123   567,814   336,971   306,895 
Cash and cash equivalents, end of period $308,491  $466,840  $308,491  $466,840 
 

Article content

B2GOLD CORP.
CONDENSED INTERIM CONSOLIDATED BALANCE SHEETS 

(Expressed in thousands of United States dollars)
(Unaudited)

 
  As at June 30, 2025 As at December 31, 2024
Assets    
Current    
Cash and cash equivalents $308,491  $336,971 
Receivables, prepaids and other  44,458   41,059 
Value-added and other tax receivables  35,866   46,173 
Inventories  561,120   477,586 
   949,935   901,789 
     
Long-term investments  128,744   76,717 
Value-added tax receivables  315,152   244,147 
Mining interests  3,596,702   3,291,435 
Investments in associates  96,395   91,417 
Long-term inventories  109,174   134,529 
Other assets  78,880   73,964 
Deferred income taxes  31,386    
  $5,306,368  $4,813,998 
Liabilities    
Current    
Accounts payable and accrued liabilities $157,819  $156,352 
Current income and other taxes payable  139,040   103,557 
Current portion of prepaid gold sales  558,165   272,781 
Current portion of long-term debt  31,405   16,419 
Current portion of derivative instruments  40,586   1,606 
Current portion of gold stream obligation  18,000   6,900 
Current portion of mine restoration provisions  6,522   7,170 
Other current liabilities  17,509   15,902 
   969,046   580,687 
     
Long-term debt  411,482   421,464 
Gold stream obligation  200,731   159,525 
Prepaid gold sales     265,329 
Mine restoration provisions  150,851   140,541 
Deferred income taxes  182,242   169,738 
Derivative instruments  32,218   2,760 
Employee benefits obligation  22,151   18,410 
Other long-term liabilities  21,104   19,847 
   1,989,825   1,778,301 
Equity    
Shareholders’ equity    
Share capital  3,526,873   3,510,271 
Contributed surplus  160,468   91,184 
Accumulated other comprehensive loss  (60,456)  (102,771)
Retained deficit  (356,943)  (515,619)
   3,269,942   2,983,065 
Non-controlling interests  46,601   52,632 
   3,316,543   3,035,697 
  $5,306,368  $4,813,998 
 

Article content

NON-IFRS MEASURES

Article content

Cash operating costs per gold ounce sold and total cash costs per gold ounce sold

Article content

‘‘Cash operating costs per gold ounce’’ and “total cash costs per gold ounce” are common financial performance measures in the gold mining industry but, as non-IFRS measures, they do not have a standardized meaning under IFRS and therefore may not be comparable to similar measures presented by other issuers. Management believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate our performance and ability to generate cash flow. Accordingly, these measures are intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. The measures, along with sales, are considered to be a key indicator of the Company’s ability to generate earnings and cash flow from its mining operations.

Article content

Cash cost figures are calculated on a sales basis in accordance with a standard developed by The Gold Institute, which was a worldwide association of suppliers of gold and gold products and included leading North American gold producers. The Gold Institute ceased operations in 2002, but the standard is the accepted standard of reporting cash cost of production in North America. Adoption of the standard is voluntary and the cost measures presented may not be comparable to other similarly titled measures of other companies. Other companies may calculate these measures differently. Cash operating costs and total cash costs per gold ounce sold are derived from amounts included in the statement of operations and include post-commercial production mine site operating costs such as mining, processing, smelting, refining, transportation costs, royalties and production taxes, less silver by-product credits. The tables below show a reconciliation of cash operating costs per gold ounce sold and total cash costs per gold ounce sold to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis (dollars in thousands):

Article content

 For the three months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total
 $$$$
     
Production costs96,12134,46829,774160,363
Royalties and production taxes61,5578,8727,27277,701
     
Total cash costs157,67843,34037,046238,064
     
Gold sold (ounces)115,18439,90055,300210,384
     
Cash operating costs per ounce ($/ gold ounce sold)834864538762
     
Total cash costs per ounce ($/ gold ounce sold)1,3691,0866701,132
 

Article content

 For the three months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity
investment
Grand
Total
 $$$$$$
       
Production costs81,48137,60232,216151,29913,221164,520
Royalties and production taxes21,6556,9104,52433,08971133,800
       
Total cash costs103,13644,51236,740184,38813,932198,320
       
Gold sold (ounces)115,28846,60048,340210,2288,267218,495
       
Cash operating costs per ounce ($/ gold ounce sold)7078076667201,599753
       
Total cash costs per ounce ($/ gold ounce sold)8959557608771,685908
 

Article content

 For the six months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total
 $$$$
     
Production costs185,14672,48464,727322,357
Royalties and production taxes91,05116,25013,206120,507
     
Total cash costs276,19788,73477,933442,864
     
Gold sold (ounces)202,99284,350107,040394,382
     
Cash operating costs per ounce ($/ gold ounce sold)912859605817
     
Total cash costs per ounce ($/ gold ounce sold)1,3611,0527281,123
 

Article content

 For the six months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity
investment
Grand
Total
 $$$$$$
       
Production costs166,58680,37361,085308,04425,126333,170
Royalties and production taxes42,05012,3008,76663,1161,56564,681
       
Total cash costs208,63692,67369,851371,16026,691397,851
       
Gold sold (ounces)239,11694,30099,790433,20619,644452,850
       
Cash operating costs per ounce ($/ gold ounce sold)6978526127111,279736
       
Total cash costs per ounce ($/ gold ounce sold)8739837008571,359879
 

Article content

Cash operating costs per gold ounce produced

Article content

In addition to cash operating costs on a per gold ounce sold basis, the Company also presents cash operating costs on a per gold ounce produced basis. Cash operating costs per gold ounce produced is derived from amounts included in the statement of operations and include post-commercial production mine site operating costs such as mining, processing, smelting, refining, transportation costs, less silver by-product credits. Cash operating costs per gold ounce produced do not include pre-commercial production from the Goose Mine. The tables below show a reconciliation of cash operating costs per gold ounce produced to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis (dollars in thousands):

Article content

 For the three months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Goose
Mine
Total
 $$$$$
      
Production costs96,12134,46829,774  160,363 
Inventory sales adjustment4,7586,151(846)1,178 11,241 
Pre-commercial production costs (1,178)(1,178)
      
Cash operating costs100,87940,61928,928  170,426 
      
Gold produced (ounces)126,36150,73851,663 692 229,454 
Less pre-commercial gold production (692)(692)
      
Adjusted gold produced (ounces)126,36150,73851,663  228,762 
      
Cash operating costs per ounce ($/ gold ounce produced)798801560  745 
        

Article content

 For the three months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity
investment
Grand
Total
 $$$$$$
       
Production costs81,48137,60232,216151,29913,221164,520
Inventory sales adjustment12,0971,41216813,67713,677
       
Cash operating costs93,57839,01432,384164,97613,221178,197
       
Gold produced (ounces)111,58344,51548,143204,2418,267212,508
       
Cash operating costs per ounce ($/ gold ounce produced)8398766738081,599839
 

Article content

 For the six months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Goose
Mine
Total
 $$$$$
      
Production costs185,14672,48464,727  322,357 
Inventory sales adjustment6,2946,779(4,592)1,178 9,659 
Pre-commercial production costs (1,178)(1,178)
      
Cash operating costs191,44079,26360,135  330,838 
      
Gold produced (ounces)220,16697,107104,241 692 422,206 
Less pre-commercial gold production (692)(692)
      
Adjusted gold produced (ounces)220,16697,107104,241  421,514 
      
Cash operating costs per ounce ($/ gold ounce produced)870816577  785 
 

Article content

 For the six months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity
investment
Grand
Total
 $$$$$$
       
Production costs166,58680,37361,085308,04425,126333,170
Inventory sales adjustment10,17518844010,80310,803
       
Cash operating costs176,76180,56161,525318,84725,126343,973
       
Gold produced (ounces)230,72494,29793,559418,58019,644438,224
       
Cash operating costs per ounce ($/ gold ounce produced)7668546587621,279785
 

Article content

All-in sustaining costs per gold ounce

Article content

In June 2013, the World Gold Council, a non-regulatory association of the world’s leading gold mining companies established to promote the use of gold to industry, consumers and investors, provided guidance for the calculation of the measure “all-in sustaining costs per gold ounce”, but as a non-IFRS measure, it does not have a standardized meaning under IFRS and therefore may not be comparable to similar measures presented by other issuers. The original World Gold Council standard became effective January 1, 2014 with further updates announced on November 16, 2018 which were effective starting January 1, 2019.

Article content

Management believes that the all-in sustaining costs per gold ounce measure provides additional insight into the costs of producing gold by capturing all of the expenditures required for the discovery, development and sustaining of gold production and allows the Company to assess its ability to support capital expenditures to sustain future production from the generation of operating cash flows. Management believes that, in addition to conventional measures prepared in accordance with IFRS, certain investors use this information to evaluate the Company’s performance and ability to generate cash flow. Accordingly, it is intended to provide additional information and should not be considered in isolation or as a substitute for measures of performance prepared in accordance with IFRS. Adoption of the standard is voluntary and the cost measures presented may not be comparable to other similarly titled measures of other companies. The Company has applied the principles of the World Gold Council recommendations and has reported all-in sustaining costs on a sales basis. Other companies may calculate these measures differently.

Article content

B2Gold defines all-in sustaining costs per ounce as the sum of post-commercial production cash operating costs, royalties and production taxes, capital expenditures and exploration costs that are sustaining in nature, sustaining lease expenditures, corporate general and administrative costs, share-based payment expenses related to restricted share units/deferred share units/performance share units/restricted phantom units (“RSUs/DSUs/PSUs/RPUs”), community relations expenditures, reclamation liability accretion and realized (gains) losses on fuel derivative contracts, all divided by the total post-commercial production gold ounces sold to arrive at a per ounce figure.

Article content

The tables below show a reconciliation of all-in sustaining costs per ounce to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis for the three months ended June 30, 2025 (dollars in thousands):

Article content

 For the three months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
CorporateTotal
 $$$$$
      
Production costs96,121 34,46829,774160,363
Royalties and production taxes61,557 8,8727,27277,701
Corporate administration3,591 54193810,71315,783
Share-based payments – RSUs/DSUs/PSUs/RPUs(1)15 4,6634,678
Community relations192 79288559
Reclamation liability accretion697 3352461,278
Realized losses on derivative contracts508 34259909
Sustaining lease expenditures(755)3252,0725432,185
Sustaining capital expenditures(2)36,308 14,7184,60755,633
Sustaining mine exploration(2) 54352406
      
Total all-in sustaining costs198,234 59,73445,60815,919319,495
      
Gold sold (ounces)115,184 39,90055,300210,384
      
All-in sustaining cost per ounce ($/ gold ounce sold)1,721 1,4978251,519
 

Article content

1) Included as a component of Share-based payments on the Consolidated statement of operations.
(2) Refer to Sustaining capital expenditures and Sustaining mine exploration reconciliations below.

Article content

The table below shows a reconciliation of sustaining capital expenditures to operating mine capital expenditures as extracted from the unaudited condensed interim consolidated financial statements for the three months ended June 30, 2025 (dollars in thousands):

Article content

 For the three months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total
 $$$$
     
Operating mine capital expenditures53,379 17,499 4,709 75,587 
Fekola underground(17,071)  (17,071)
Other (2,781)(102)(2,883)
     
Sustaining capital expenditures36,308 14,718 4,607 55,633 
 

Article content

The table below shows a reconciliation of sustaining mine exploration to operating mine exploration as extracted from the unaudited condensed interim consolidated financial statements for the three months ended June 30, 2025 (dollars in thousands):

Article content

 For the three months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total
 $$$$
     
Operating mine exploration531 2,382 2,913 
Regional exploration(477)(2,030)(2,507)
     
Sustaining mine exploration54 352 406 
 

Article content

The table below shows a reconciliation of all-in sustaining costs per ounce to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis for the three months ended June 30, 2024 (dollars in thousands):

Article content

 For the three months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
CorporateTotalCalibre equity
investment
Grand
Total
 $$$$$$$
        
Production costs81,481 37,602 32,216 151,299 13,221164,520 
Royalties and production taxes21,655 6,910 4,524 33,089 71133,800 
Corporate administration2,548 548 1,406 8,46612,968 90213,870 
Share-based payments – RSUs/DSUs/PSUs/RPUs(1)34   4,0234,057 4,057 
Community relations106 17 319 442 442 
Reclamation liability accretion458 313 252 1,023 1,023 
Realized gains on derivative contracts(202)(108) (310)(310)
Sustaining lease expenditures83 309 236 5121,140 1,140 
Sustaining capital expenditures(2)38,065 6,428 11,605 56,098 63756,735 
Sustaining mine exploration(2)838 864 (76)1,626 1,626 
        
Total all-in sustaining costs145,066 52,883 50,482 13,001261,432 15,471276,903 
        
Gold sold (ounces)115,288 46,600 48,340 210,228 8,267218,495 
        
All-in sustaining cost per ounce ($/ gold ounce sold)1,258 1,135 1,044 1,244 1,8711,267 
 

Article content

(1) Included as a component of Share-based payments on the Consolidated
statement of operations.
(2) Refer to Sustaining capital expenditures and Sustaining mine exploration reconciliations below

Article content

The table below shows a reconciliation of sustaining capital expenditures to operating mine capital expenditures as extracted from the unaudited condensed interim consolidated financial statements for the three months ended June 30, 2024 (dollars in thousands):

Article content

 For the three months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity
investment
Grand
Total
 $$$$$$
       
Operating mine capital expenditures53,179 6,507 11,706 71,392 63772,029 
Fekola underground(14,772)  (14,772)(14,772)
Road construction(342)  (342)(342)
Land acquisitions (49) (49)(49)
Other (30)(101)(131)(131)
       
Sustaining capital expenditures38,065 6,428 11,605 56,098 63756,735 
 

Article content

The table below shows a reconciliation of sustaining mine exploration to operating mine exploration as extracted from the unaudited condensed interim consolidated financial statements for the three months ended June 30, 2024 (dollars in thousands):

Article content

 For the three months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity
investment
Grand
Total
 $$$$$$
       
Operating mine exploration838928 1,514 3,280 3,280 
Regional exploration(64)(1,590)(1,654)(1,654)
       
Sustaining mine exploration838864 (76)1,626 1,626 
 

Article content

The tables below show a reconciliation of all-in sustaining costs per ounce to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis for the six months ended June 30, 2025 (dollars in thousands):

Article content

 For the six months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
CorporateTotal
 $$$$$
      
Production costs185,14672,48464,727322,357
Royalties and production taxes91,05116,25013,206120,507
Corporate administration6,5281,0682,28717,70227,585
Share-based payments – RSUs/DSUs/PSUs/RPUs(1)308,2018,231
Community relations6741817031,558
Reclamation liability accretion1,3126805092,501
Realized losses on derivative contracts621381821,084
Sustaining lease expenditures1646412,4129704,187
Sustaining capital expenditures(2)82,83421,5808,214112,628
Sustaining mine exploration(2)70845915
      
Total all-in sustaining costs368,360113,33592,98526,873601,553
      
Gold sold (ounces)202,99284,350107,040394,382
      
All-in sustaining cost per ounce ($/ gold ounce sold)1,8151,3448691,525
 

Article content

(1) Included as a component of Share-based payments on the Consolidated statement of operations.
(2) Refer to Sustaining capital expenditures and Sustaining mine exploration reconciliations below

Article content

The table below shows a reconciliation of sustaining capital expenditures to operating mine capital expenditures as extracted from the unaudited condensed interim consolidated financial statements for the six months ended June 30, 2025 (dollars in thousands):

Article content

 For the six months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total
 $$$$
     
Operating mine capital expenditures117,382 25,232 8,316 150,930 
Fekola underground(34,548)  (34,548)
Other (3,652)(102)(3,754)
     
Sustaining capital expenditures82,834 21,580 8,214 112,628 
 

Article content

The table below shows a reconciliation of sustaining mine exploration to operating mine exploration as extracted from the unaudited condensed interim consolidated financial statements for the six months ended June 30, 2025 (dollars in thousands)

Article content

 For the six months ended June 30, 2025
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
Total
 $$$$
     
Operating mine exploration951 4,213 5,164 
Regional exploration(881)(3,368)(4,249)
     
Sustaining mine exploration70 845 915 
 

Article content

The tables below show a reconciliation of all-in sustaining costs per ounce to production costs as extracted from the unaudited condensed interim consolidated financial statements on a consolidated and a mine-by-mine basis for the six months ended June 30, 2024 (dollars in thousands):

Article content

 For the six months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
CorporateTotalCalibre equity
investment
Grand
Total
 $$$$$$$
        
Production costs166,586 80,373 61,085 308,044 25,126333,170 
Royalties and production taxes42,050 12,300 8,766 63,116 1,56564,681 
Corporate administration5,275 1,062 2,886 17,88327,106 1,46328,569 
Share-based payments – RSUs/DSUs/PSUs/RPUs(1)67   8,9969,063 9,063 
Community relations251 30 650 931 931 
Reclamation liability accretion893 614 490 1,997 1,997 
Realized gains on derivative contracts(420)(252)(31)(703)(703)
Sustaining lease expenditures167 627 790 1,0042,588 2,588 
Sustaining capital expenditures(2)105,935 14,677 24,503 145,115 2,392147,507 
Sustaining mine exploration(2)2,140 1,598 626 4,364 4,364 
        
Total all-in sustaining costs322,944 111,029 99,765 27,883561,621 30,546592,167 
        
Gold sold (ounces)239,116 94,300 99,790 433,206 19,644452,850 
        
All-in sustaining cost per ounce ($/ gold ounce sold)1,351 1,177 1,000 1,296 1,5551,308 
 

Article content

(1) Included as a component of Share-based payments on the Consolidated statement of operations.
(2) Refer to Sustaining capital expenditures and Sustaining mine exploration reconciliations below

Article content

The table below shows a reconciliation of sustaining capital expenditures to operating mine capital expenditures as extracted from the unaudited condensed interim consolidated financial statements for the six months ended June 30, 2024 (dollars in thousands):

Article content

 For the six months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity
investment
Grand
Total
 $$$$$$
       
Operating mine capital expenditures133,741 15,037 25,519 174,297 2,392176,689 
Fekola underground(25,876)  (25,876)(25,876)
Road construction(1,930)  (1,930)(1,930)
Land acquisition (120) (120)(120)
Other (240)(1,016)(1,256)(1,256)
       
Sustaining capital expenditures105,935 14,677 24,503 145,115 2,392147,507 
 

Article content

The table below shows a reconciliation of sustaining mine exploration to operating mine exploration as extracted from the unaudited condensed interim consolidated financial statements for the six months ended June 30, 2024 (dollars in thousands):

Article content

 For the six months ended June 30, 2024
 Fekola
Mine
Masbate
Mine
Otjikoto
Mine
TotalCalibre equity
investment
Grand
Total
 $$$$$$
       
Operating mine exploration2,1401,749 3,303 7,192 7,192 
Regional exploration(151)(2,677)(2,828)(2,828)
       
Sustaining mine exploration2,1401,598 626 4,364 4,364 
 

Article content

Adjusted net income and adjusted earnings per share – basic

Article content

Adjusted net income and adjusted earnings per share – basic are non-IFRS measures that do not have a standardized meaning prescribed by IFRS and therefore may not be comparable to similar measures presented by other issuers. The Company defines adjusted net income as net income attributable to shareholders of the Company adjusted for non-recurring items and also significant recurring non-cash items. The Company defines adjusted earnings per share – basic as adjusted net income divided by the basic weighted number of common shares outstanding.

Article content

Management believes that the presentation of adjusted net income and adjusted earnings per share – basic is appropriate to provide additional information to investors regarding items that we do not expect to continue at the same level in the future or that management does not believe to be a reflection of the Company’s ongoing operating performance. Management further believes that its presentation of these non-IFRS financial measures provide information that is useful to investors because they are important indicators of the strength of our operations and the performance of our core business. Accordingly, it is intended to provide additional information and should not be considered in isolation as a substitute for measures of performance prepared in accordance with IFRS. Other companies may calculate this measure differently.

Article content

A reconciliation of net income (loss) to adjusted net income as extracted from the unaudited condensed interim consolidated financial statements is set out in the table below:

Article content

 Three months endedSix months ended
 June 30,June 30,
 2025202420252024
 $$$$
 (000’s)(000’s)(000’s)(000’s)
     
Net income (loss) attributable to shareholders of the Company for the period:154,424 (24,004)212,011 15,747 
     
Adjustments for non-recurring and significant recurring non-cash items:    
Unrealized losses (gains) on derivative instruments19,780 (119)70,655 (1)
Change in fair value of gold stream21,754 8,387 52,306 19,239 
Realized gain on total return swap  (7,731) 
Write-down of mining interests 636 5,118 636 
Impairment of long-lived assets 197,141  197,141 
Gain on sale of mining interests (48,662) (48,662)
Gain on sale of shares in associate (16,822) (16,822)
(Gain) loss on dilution of associate (998) 8,984 
Deferred income tax recovery(33,119)(37,110)(47,670)(16,310)
     
Adjusted net income attributable to shareholders of the Company for the period162,839 78,449 284,689 159,952 
     
Basic weighted average number of common shares outstanding (in thousands)1,321,740 1,307,176 1,320,074 1,305,183 
     
Adjusted net earnings attributable to shareholders of the Company per share–basic ($/share)0.12 0.06 0.22 0.12 
 

Article content

Article content

Article content

Article content

Article content

Article content

Article content

For more information on B2Gold please visit the Company website at www.b2gold.com or contact: Michael McDonald VP, IR, Corporate Development, & Treasury +1 604-681-8371 [email protected] Cherry DeGeer Director, Corporate Communications +1 604-681-8371 [email protected]